Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
230
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0060 # 05 Y:1986 | 05 | 1986 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,064 | $440 | Not Implemented |
MA0060 # 06 Y:1986 | 06 | 1986 | REPAIR OR REPLACE STEAM TRAPS | $8,227 | $195 | Not Implemented |
MA0060 # 07 Y:1986 | 07 | 1986 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $748 | $1,107 | Not Implemented |
MA0060 # 08 Y:1986 | 08 | 1986 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $510 | $340 | Not Implemented |
MA0060 # 09 Y:1986 | 09 | 1986 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $808 | $2,200 | Not Implemented |
MA0061 # 01 Y:1986 | 01 | 1986 | USE RADIANT HEATER FOR SPOT HEATING | $721 | $800 | Implemented |
MA0061 # 02 Y:1986 | 02 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,705 | $300 | Implemented |
MA0061 # 03 Y:1986 | 03 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,390 | $300 | Implemented |
MA0061 # 04 Y:1986 | 04 | 1986 | INSTALL STORM WINDOWS AND DOORS | $2,523 | $6,945 | Implemented |
KU0193 # 01 Y:1986 | 01 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,876 | $5,003 | Implemented |
KU0193 # 02 Y:1986 | 02 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $769 | $100 | Implemented |
KU0193 # 03 Y:1986 | 03 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $4,524 | $667 | Implemented |
KU0193 # 04 Y:1986 | 04 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $273 | $0 | Not Implemented |
KU0193 # 05 Y:1986 | 05 | 1986 | INSTALL AUTOMATIC STACK DAMPER | $1,097 | $500 | Implemented |
KU0193 # 06 Y:1986 | 06 | 1986 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $802 | $52 | Not Implemented |
KU0193 # 07 Y:1986 | 07 | 1986 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $178 | $75 | Not Implemented |
KU0193 # 08 Y:1986 | 08 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $111 | $0 | Implemented |
KU0194 # 01 Y:1986 | 01 | 1986 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $1,687 | $0 | Implemented |
KU0194 # 02 Y:1986 | 02 | 1986 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,003 | $1,575 | Implemented |
KU0194 # 03 Y:1986 | 03 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $393 | $50 | Implemented |
MA0057 # 01 Y:1986 | 01 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,191 | $2,500 | Implemented |
MA0057 # 02 Y:1986 | 02 | 1986 | REDUCE GLAZED AREAS IN BUILDINGS | $3,959 | $8,455 | Implemented |
MA0057 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $377 | $300 | Implemented |
MA0057 # 04 Y:1986 | 04 | 1986 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,512 | $0 | Not Implemented |
MA0057 # 05 Y:1986 | 05 | 1986 | USE FLUE GASES IN RADIANT HEATER FOR SPACE HEATING, OVENS, ETC | $2,262 | $7,500 | Implemented |