Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
383
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AR0148 # 03 Y:1998 | 03 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,475 | $0 | Not Implemented |
AR0148 # 04 Y:1998 | 04 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,792 | $850 | Not Implemented |
AR0148 # 05 Y:1998 | 05 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $40,673 | $1,200 | Implemented |
AR0148 # 06 Y:1998 | 06 | 1998 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $39,295 | $91,825 | Implemented |
AR0148 # 07 Y:1998 | 07 | 1998 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $3,600 | $6,000 | Not Implemented |
AR0148 # 08 Y:1998 | 08 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $4,787 | $1,000 | Implemented |
AR0148 # 09 Y:1998 | 09 | 1998 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $4,143 | $0 | Not Implemented |
OK0550 # 01 Y:1998 | 01 | 1998 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $100,207 | $0 | Not Implemented |
OK0550 # 02 Y:1998 | 02 | 1998 | REDESIGN PROCESS | $26,768 | $20,000 | Not Implemented |
OK0550 # 10 Y:1998 | 10 | 1998 | INSULATE BARE EQUIPMENT | $197 | $134 | Implemented |
OK0550 # 09 Y:1998 | 09 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $518 | $1,610 | Not Implemented |
OK0550 # 08 Y:1998 | 08 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,920 | $3,006 | Not Implemented |
OK0550 # 07 Y:1998 | 07 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,071 | $8,400 | Implemented |
OK0550 # 06 Y:1998 | 06 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $3,888 | $9,700 | Not Implemented |
OK0550 # 05 Y:1998 | 05 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $18,120 | $0 | Implemented |
OK0550 # 04 Y:1998 | 04 | 1998 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,343 | $4,000 | Implemented |
OK0550 # 03 Y:1998 | 03 | 1998 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $8,393 | $1,945 | Implemented |
AR0137 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,861 | $190 | Implemented |
AR0137 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,790 | $628 | Implemented |
AR0137 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,133 | $2,052 | Implemented |
AR0137 # 04 Y:1998 | 04 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,002 | $0 | Implemented |
AR0137 # 05 Y:1998 | 05 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,811 | $215 | Implemented |
AR0137 # 06 Y:1998 | 06 | 1998 | RECOVER AND REUSE COOLING WATER | $4,245 | $800 | Implemented |
AR0137 # 07 Y:1998 | 07 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,832 | $400 | Not Implemented |
AR0137 # 08 Y:1998 | 08 | 1998 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $9,565 | $4,500 | Implemented |