IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

534

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0314 # 04 Y:2006 04 2006 USE RADIANT HEATER FOR SPOT HEATING $7,677 $9,600 Not Implemented
BD0314 # 05 Y:2006 05 2006 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $1,824 $1,200 Not Implemented
BD0314 # 06 Y:2006 06 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,382 $4,955 Not Implemented
BD0314 # 07 Y:2006 07 2006 INSTALL OCCUPANCY SENSORS $1,221 $525 Not Implemented
BD0314 # 08 Y:2006 08 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $421 $1,230 Not Implemented
UM0301 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $9,958 $30,000 Not Implemented
UM0301 # 02 Y:2006 02 2006 INSULATE BARE EQUIPMENT $6,754 $1,971 Implemented
UM0301 # 03 Y:2006 03 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $6,429 $9,875 Not Implemented
UM0301 # 04 Y:2006 04 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,344 $500 Not Implemented
UM0301 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,457 $375 Implemented
UM0301 # 06 Y:2006 06 2006 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $4,498 $738 Not Implemented
UM0301 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,325 $0 Implemented
UM0301 # 08 Y:2006 08 2006 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $1,415 $1,363 Not Implemented
UM0301 # 09 Y:2006 09 2006 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING $328 $328 Not Implemented
UM0301 # 10 Y:2006 10 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,062 $300 Not Implemented
UM0301 # 11 Y:2006 11 2006 RECOVER WASTE HEAT FROM EQUIPMENT $218 $500 Not Implemented
AS0423 # 01 Y:2006 01 2006 $205,767 $2,100,000 n/a
AS0423 # 02 Y:2006 02 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $13,786 $1,000 n/a
AS0423 # 03 Y:2006 03 2006 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $13,786 $13,000 n/a
AS0423 # 04 Y:2006 04 2006 UPGRADE CONTROLS ON COMPRESSORS $13,316 $10,000 n/a
AS0423 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,912 $10,000 n/a
AS0423 # 06 Y:2006 06 2006 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $8,401 $16,000 n/a
UM0300 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $15,780 $14,167 Implemented
UM0300 # 02 Y:2006 02 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $7,203 $2,500 Implemented
UM0300 # 03 Y:2006 03 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $2,520 $515 Implemented