Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
523
matching recommendationsSIC | 341 | Metal Cans And Shipping Containers |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0293 # 05 Y:2024 | 05 | 2024 | USE OPTIMUM THICKNESS INSULATION | $17,140 | $38,685 | Implemented |
IC0293 # 02 Y:2024 | 02 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,300 | $1,110 | Implemented |
IC0293 # 04 Y:2024 | 04 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $384 | $338 | Implemented |
SF0607 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,524 | $11,610 | Implemented |
SF0607 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,963 | $344 | Implemented |
SF0607 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,168 | $0 | Implemented |
SF0607 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,399 | $8,086 | Implemented |
SF0607 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $41,060 | $346,427 | Implemented |
UD1059 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,947 | $14,000 | Implemented |
UD1059 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $25,386 | $1,200 | Implemented |
UD1059 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $20,047 | $800 | Implemented |
UD1059 # 01 Y:2023 | 01 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $43,663 | $1,000 | Implemented |
LE0549 # 02 Y:2023 | 02 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,466 | $8,000 | Implemented |
LE0549 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,374 | $56,502 | Implemented |
LE0549 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,236 | $2,600 | Implemented |
LE0549 # 03 Y:2023 | 03 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $251 | $1,200 | Implemented |
NL0076 # 06 Y:2022 | 06 | 2022 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $4,338 | $7,210 | Implemented |
NL0076 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,256 | $4,500 | Implemented |
NL0076 # 05 Y:2022 | 05 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,194 | $140 | Implemented |
MZ0336 # 05 Y:2023 | 05 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $31,782 | $11,200 | Implemented |
MZ0336 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,175 | $53,900 | Implemented |
MZ0336 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $1,963 | $2,020 | Implemented |
WM0185 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $471 | $0 | Implemented |
WM0185 # 08 Y:2023 | 08 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $426 | $0 | Implemented |
WM0185 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $443 | $1,250 | Implemented |