Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
47
matching recommendationsSIC | 342 | Cutlery, Handtools, And Hardware |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0651 # 02 Y:1998 | 02 | 1998 | COVER OPEN TANKS | $21,415 | $6,174 | Not Implemented |
GT0651 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,874 | $52,766 | Not Implemented |
GT0651 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,505 | $3,933 | Not Implemented |
GT0651 # 05 Y:1998 | 05 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,004 | $413 | Not Implemented |
GT0651 # 06 Y:1998 | 06 | 1998 | RECOVER AND REUSE WASTE MATERIAL | $16,208 | $38,860 | Not Implemented |
GT0651 # 07 Y:1998 | 07 | 1998 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $2,099 | $0 | Not Implemented |
GT0651 # 08 Y:1998 | 08 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $105,300 | $120,000 | Not Implemented |
GT0651 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,260 | $3,100 | Not Implemented |
KU0511 # 06 Y:1998 | 06 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,670 | $3,960 | Implemented |
KU0511 # 15 Y:1998 | 15 | 1998 | PURCHASE RE-CONDITIONED MATERIAL INSTEAD OF NEW | $1,300 | $800 | Not Implemented |
KU0511 # 14 Y:1998 | 14 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $4,120 | $4,400 | Not Implemented |
KU0511 # 13 Y:1998 | 13 | 1998 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $4,980 | $10,000 | Implemented |
KU0511 # 12 Y:1998 | 12 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $5,560 | $690 | Implemented |
KU0511 # 11 Y:1998 | 11 | 1998 | AUTOMATE FINISHING PROCESS | $12,150 | $42,810 | Not Implemented |
KU0511 # 10 Y:1998 | 10 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $15,070 | $17,000 | Implemented |
KU0511 # 09 Y:1998 | 09 | 1998 | MODIFY STARTUP/SHUTDOWN TIMES | $75,530 | $0 | Not Implemented |
KU0511 # 08 Y:1998 | 08 | 1998 | INSULATE BARE EQUIPMENT | $230 | $680 | Implemented |
KU0511 # 07 Y:1998 | 07 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $590 | $360 | Implemented |
KU0511 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,560 | $800 | Implemented |
KU0511 # 04 Y:1998 | 04 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,570 | $2,550 | Implemented |
KU0511 # 03 Y:1998 | 03 | 1998 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $3,080 | $3,040 | Implemented |
KU0511 # 02 Y:1998 | 02 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $8,600 | $32,720 | Not Implemented |
KU0511 # 01 Y:1998 | 01 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $25,680 | $19,610 | Implemented |
TN0639 # 02 Y:1998 | 02 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $5,440 | $3,440 | Implemented |
TN0639 # 01 Y:1998 | 01 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $74,290 | $26,180 | Implemented |