IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,509

matching recommendations
Reset
SIC 344 Fabricated Structural Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0306 # 02 Y:2002 02 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,006 $240 Not Implemented
SD0306 # 03 Y:2002 03 2002 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $3,708 $1,000 Not Implemented
SD0306 # 04 Y:2002 04 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,521 $6,822 Not Implemented
SD0306 # 05 Y:2002 05 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,468 $0 Implemented
SD0306 # 06 Y:2002 06 2002 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $2,478 $5,000 Not Implemented
UU0028 # 01 Y:2002 01 2002 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $986 $0 Implemented
UU0028 # 02 Y:2002 02 2002 OPTIMIZE PLANT POWER FACTOR $5,590 $9,800 Implemented
UU0028 # 03 Y:2002 03 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $30,500 $7,600 Implemented
UU0028 # 04 Y:2002 04 2002 RECOVER WASTE HEAT FROM EQUIPMENT $1,450 $700 Implemented
UU0028 # 05 Y:2002 05 2002 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $844 $406 Implemented
UU0028 # 06 Y:2002 06 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,400 $2,000 Implemented
UU0028 # 07 Y:2002 07 2002 INSTALL SKYLIGHTS $17,689 $2,800 Not Implemented
UU0028 # 08 Y:2002 08 2002 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $147,880 $100,000 Not Implemented
UM0222 # 01 Y:2002 01 2002 LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE $28,900 $10,000 Implemented
UM0222 # 02 Y:2002 02 2002 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $23,074 $1,750 Implemented
UM0222 # 03 Y:2002 03 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,900 $1,275 Implemented
UM0222 # 04 Y:2002 04 2002 AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM $2,523 $2,000 Not Implemented
UM0222 # 05 Y:2002 05 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,261 $4,000 Not Implemented
UF0308 # 01 Y:2002 01 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,465 $10,121 n/a
UF0308 # 02 Y:2002 02 2002 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,612 $500 n/a
UF0308 # 03 Y:2002 03 2002 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,366 $0 n/a
UF0308 # 04 Y:2002 04 2002 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,184 $1,033 n/a
UF0308 # 05 Y:2002 05 2002 INSULATE BARE EQUIPMENT $4,591 $291 n/a
UF0308 # 06 Y:2002 06 2002 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $5,687 $19,500 n/a
UF0308 # 07 Y:2002 07 2002 INSTALL AUTOMATIC PART STORAGE / RETREVAL SYSTEM $4,770 $864 n/a