Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
75
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0542 # 01 Y:2008 | 01 | 2008 | Solar | $112,205 | $783,772 | Not Implemented |
OR0542 # 03 Y:2008 | 03 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,350 | $385 | Not Implemented |
OR0542 # 04 Y:2008 | 04 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,260 | $6,902 | Not Implemented |
OR0542 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,132 | $9,045 | Not Implemented |
OR0542 # 06 Y:2008 | 06 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,527 | $0 | Not Implemented |
OR0350 # 03 Y:1999 | 03 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $2,030 | $1,150 | Not Implemented |
OR0350 # 04 Y:1999 | 04 | 1999 | OPTIMIZE PLANT POWER FACTOR | $167 | $600 | Not Implemented |
OR0350 # 02 Y:1999 | 02 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,264 | $16,230 | Not Implemented |
OR0350 # 01 Y:1999 | 01 | 1999 | MODIFY CURRENT INCENTIVE PROGRAM | $23,000 | $13,300 | Not Implemented |
OR0319 # 02 Y:1998 | 02 | 1998 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $32,660 | $300,000 | Implemented |
OR0319 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $355 | $1,750 | Implemented |
OR0319 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $833 | $1,000 | Implemented |
OR0319 # 01 Y:1998 | 01 | 1998 | ELIMINATE SHIFT | $200,000 | $2,500 | Implemented |
OR0319 # 03 Y:1998 | 03 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $31,569 | $931 | Implemented |
OR0273 # 02 Y:1996 | 02 | 1996 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $1,544 | $1,000 | Implemented |
OR0273 # 01 Y:1996 | 01 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,150 | $6,000 | Not Implemented |
OR0273 # 03 Y:1996 | 03 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $803 | $1,775 | Implemented |
OR0273 # 04 Y:1996 | 04 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $947 | $5,575 | Not Implemented |
OR0273 # 05 Y:1996 | 05 | 1996 | USE OTHER WASTE CONCENTRATION METHODS | $45,735 | $67,500 | Not Implemented |
OR0247 # 06 Y:1995 | 06 | 1995 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $6,900 | $0 | Implemented |
OR0247 # 05 Y:1995 | 05 | 1995 | REPLACE WATER COOLING ON PROCESSES WITH AIR COOLING | $23,384 | $10,772 | Implemented |
OR0247 # 04 Y:1995 | 04 | 1995 | OPTIMIZE PLANT POWER FACTOR | $2,538 | $7,200 | Not Implemented |
OR0247 # 03 Y:1995 | 03 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $374 | $521 | Implemented |
OR0247 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,211 | $3,000 | Implemented |
OR0247 # 01 Y:1995 | 01 | 1995 | UPGRADE CONTROLS ON COMPRESSORS | $10,230 | $5,900 | Implemented |