IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

291

matching recommendations
Reset
SIC 344 Fabricated Structural Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0511 # 05 Y:1996 05 1996 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $20,723 $15,008 Implemented
OK0511 # 04 Y:1996 04 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,173 $797 Implemented
OK0511 # 03 Y:1996 03 1996 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,844 $260 Implemented
OK0511 # 02 Y:1996 02 1996 INSTALL TIMERS AND/OR THERMOSTATS $113 $124 Implemented
OK0511 # 01 Y:1996 01 1996 USE RADIANT HEATER FOR SPOT HEATING $3,504 $18,090 Not Implemented
OK0495 # 07 Y:1996 07 1996 TREAT AND REUSE RINSE WATERS $3,524 $40,000 Implemented
OK0495 # 06 Y:1996 06 1996 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $246 $120 Implemented
OK0495 # 05 Y:1996 05 1996 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $232 $244 Implemented
OK0495 # 04 Y:1996 04 1996 INSTALL OCCUPANCY SENSORS $104 $132 Not Implemented
OK0495 # 03 Y:1996 03 1996 INSTALL SPECTRAL REFLECTORS / DELAMP $854 $65 Not Implemented
OK0495 # 02 Y:1996 02 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $66 $228 Not Implemented
OK0495 # 01 Y:1996 01 1996 INSTALL SET-BACK TIMERS $5,943 $1,050 Implemented
OK0476 # 05 Y:1995 05 1995 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $10,856 $36,000 Not Implemented
OK0475 # 01 Y:1995 01 1995 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $10,960 $1,800 Not Implemented
OK0475 # 02 Y:1995 02 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $600 $3,553 Implemented
OK0475 # 03 Y:1995 03 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $513 $50 Implemented
OK0475 # 04 Y:1995 04 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,280 $1,819 Implemented
OK0475 # 05 Y:1995 05 1995 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $14,929 $30,000 Not Implemented
OK0476 # 04 Y:1995 04 1995 INSTALL SET-BACK TIMERS $553 $200 Implemented
OK0476 # 01 Y:1995 01 1995 USE POWER DURING OFF-PEAK PERIODS $3,319 $0 Not Implemented
OK0476 # 02 Y:1995 02 1995 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,650 $90 Implemented
OK0476 # 03 Y:1995 03 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $900 $655 Implemented
OK0474 # 01 Y:1995 01 1995 REPAIR AND ELIMINATE STEAM LEAKS $4,457 $4,457 Implemented
OK0474 # 02 Y:1995 02 1995 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $3,632 $3,553 Implemented
OK0474 # 04 Y:1995 04 1995 INSTALL / REPAIR INSULATION ON STEAM LINES $1,280 $1,819 Implemented