Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
43
matching recommendationsSIC | 3441 | Fabricated Structural Metal |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1027 # 04 Y:2021 | 04 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,522 | $0 | Not Implemented |
UD1027 # 03 Y:2021 | 03 | 2021 | RECOVER AND REUSE COOLING WATER | $7,993 | $0 | Not Implemented |
UD1027 # 02 Y:2021 | 02 | 2021 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $11,486 | $1,000 | Not Implemented |
UD1027 # 01 Y:2021 | 01 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,612 | $0 | Implemented |
UD1027 # 08 Y:2021 | 08 | 2021 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $2,481 | $4,300 | Not Implemented |
UD1027 # 07 Y:2021 | 07 | 2021 | REPAIR OR REPLACE STEAM TRAPS | $6,067 | $4,875 | Not Implemented |
UD1027 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,842 | $1,000 | Implemented |
UD1027 # 09 Y:2021 | 09 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,013 | $65,250 | Implemented |
UD1027 # 06 Y:2021 | 06 | 2021 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,443 | $0 | Not Implemented |
UD1027 # 10 Y:2021 | 10 | 2021 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $10,735 | $43,000 | Not Implemented |
UD0928 # 07 Y:2015 | 07 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $154,780 | $150,000 | Not Implemented |
UD0928 # 12 Y:2015 | 12 | 2015 | ADJUST PH FOR NEUTRALIZATION | $68,888 | $34,000 | Not Implemented |
UD0928 # 11 Y:2015 | 11 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,007 | $1,000 | Not Implemented |
UD0928 # 10 Y:2015 | 10 | 2015 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $5,622 | $25,000 | Not Implemented |
UD0928 # 09 Y:2015 | 09 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,264 | $30,000 | Not Implemented |
UD0928 # 08 Y:2015 | 08 | 2015 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $11,986 | $18,300 | Not Implemented |
UD0928 # 06 Y:2015 | 06 | 2015 | COVER OPEN TANKS | $2,876 | $2,196 | Not Implemented |
UD0928 # 05 Y:2015 | 05 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $52,184 | $105,000 | Not Implemented |
UD0928 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $2,735 | $12,995 | Not Implemented |
UD0928 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $314,492 | $152,750 | Not Implemented |
UD0928 # 02 Y:2015 | 02 | 2015 | USE RADIANT HEATER FOR SPOT HEATING | $153,677 | $48,000 | Not Implemented |
UD0928 # 01 Y:2015 | 01 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,389 | $0 | Not Implemented |
WV0494 # 03 Y:2014 | 03 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,592 | $1,010 | Implemented |
WV0494 # 02 Y:2014 | 02 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,532 | $51,000 | Implemented |
WV0494 # 01 Y:2014 | 01 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $14,985 | $5,400 | Not Implemented |