Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
34
matching recommendationsSIC | 3443 | Fabricated Plate Work (boiler Shops) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0722 # 08 Y:2016 | 08 | 2016 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,900 | $500 | n/a |
CO0722 # 01 Y:2016 | 01 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,390 | $0 | n/a |
CO0722 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $880 | $110 | n/a |
CO0722 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,500 | $21,280 | n/a |
CO0722 # 04 Y:2016 | 04 | 2016 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $5,910 | $560 | n/a |
CO0722 # 05 Y:2016 | 05 | 2016 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $4,830 | $6,980 | n/a |
CO0722 # 06 Y:2016 | 06 | 2016 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,180 | $0 | n/a |
CO0722 # 07 Y:2016 | 07 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $920 | $5,520 | n/a |
CO0405 # 07 Y:1997 | 07 | 1997 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $170 | $0 | Not Implemented |
CO0405 # 06 Y:1997 | 06 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $410 | $0 | Not Implemented |
CO0405 # 05 Y:1997 | 05 | 1997 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $1,820 | $0 | Not Implemented |
CO0405 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $800 | $330 | Not Implemented |
CO0405 # 03 Y:1997 | 03 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $840 | $0 | Not Implemented |
CO0405 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $835 | $90 | Not Implemented |
CO0405 # 01 Y:1997 | 01 | 1997 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $5,110 | $5,390 | Not Implemented |
CO0338 # 04 Y:1995 | 04 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $540 | $1,130 | Implemented |
CO0338 # 05 Y:1995 | 05 | 1995 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $340 | $220 | Not Implemented |
CO0338 # 03 Y:1995 | 03 | 1995 | REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER | $1,070 | $1,000 | Not Implemented |
CO0338 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,520 | $13,510 | Implemented |
CO0338 # 01 Y:1995 | 01 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,620 | $410 | Implemented |
CO0246 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,500 | $29,730 | Implemented |
CO0246 # 01 Y:1992 | 01 | 1992 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,100 | $250 | Implemented |
CO0246 # 02 Y:1992 | 02 | 1992 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $820 | $5 | Implemented |
CO0246 # 03 Y:1992 | 03 | 1992 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,120 | $1,300 | Implemented |
CO0246 # 04 Y:1992 | 04 | 1992 | INSTALL TIMERS AND/OR THERMOSTATS | $190 | $10 | Implemented |