Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,236
matching recommendationsSIC | 3443 | Fabricated Plate Work (boiler Shops) |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0225 # 06 Y:2001 | 06 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,187 | $2,058 | Not Implemented |
WV0225 # 15 Y:2001 | 15 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $35,000 | $10,440 | Not Implemented |
WV0225 # 14 Y:2001 | 14 | 2001 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $1,001 | $2,500 | Implemented |
WV0225 # 13 Y:2001 | 13 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $275 | $1,044 | Implemented |
WV0225 # 12 Y:2001 | 12 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $699 | $2,655 | Not Implemented |
WV0225 # 11 Y:2001 | 11 | 2001 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $2,221 | $4,450 | Not Implemented |
WV0225 # 10 Y:2001 | 10 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $683 | $250 | Implemented |
WV0225 # 09 Y:2001 | 09 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $733 | $104 | Implemented |
WV0225 # 08 Y:2001 | 08 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $453 | $44 | Implemented |
WV0225 # 07 Y:2001 | 07 | 2001 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $1,519 | $1,500 | Not Implemented |
WV0225 # 05 Y:2001 | 05 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $674 | $386 | Implemented |
WV0225 # 04 Y:2001 | 04 | 2001 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $4,177 | $1,320 | Implemented |
WV0225 # 03 Y:2001 | 03 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $8,134 | $528 | Implemented |
WV0225 # 02 Y:2001 | 02 | 2001 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $6,690 | $5,084 | Not Implemented |
WV0225 # 01 Y:2001 | 01 | 2001 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $720 | $4,100 | Not Implemented |
OK0620 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,592 | $615 | Implemented |
OK0620 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $238 | $1,470 | Implemented |
OK0620 # 03 Y:2001 | 03 | 2001 | INSTALL OCCUPANCY SENSORS | $129 | $240 | Not Implemented |
OK0620 # 04 Y:2001 | 04 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $1,442 | $200 | Implemented |
OK0620 # 05 Y:2001 | 05 | 2001 | INSTALL SET-BACK TIMERS | $8,700 | $1,170 | Implemented |
OK0620 # 06 Y:2001 | 06 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,130 | $40 | Implemented |
OK0620 # 07 Y:2001 | 07 | 2001 | INCREASE USE OF AUTOMATION | $4,160 | $38,900 | Not Implemented |
IA0271 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,886 | $0 | Implemented |
IA0271 # 02 Y:2001 | 02 | 2001 | INSTALL OCCUPANCY SENSORS | $789 | $1,131 | Not Implemented |
IA0271 # 03 Y:2001 | 03 | 2001 | AIR CONDITION ONLY SPACE NECESSARY | $1,333 | $384 | Implemented |