IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,512

matching recommendations
Reset
SIC 3444 Sheet Metalwork
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0237 # 05 Y:2021 05 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $985 $141 Implemented
UF0561 # 01 Y:2020 01 2020 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $136,163 $259,600 Implemented
UF0561 # 02 Y:2020 02 2020 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $15,219 $20,000 Implemented
UF0561 # 03 Y:2020 03 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,460 $31,240 Implemented
UF0561 # 04 Y:2020 04 2020 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $11,358 $2,343 Implemented
UF0561 # 05 Y:2020 05 2020 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $7,808 $1,360 Implemented
UF0561 # 06 Y:2020 06 2020 USE PHOTOCELL CONTROLS $7,062 $4,098 Implemented
UF0561 # 07 Y:2020 07 2020 USE COMPRESSOR AIR FILTERS $2,064 $5,898 Implemented
UF0561 # 08 Y:2020 08 2020 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,057 $930 Implemented
UF0561 # 09 Y:2020 09 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,043 $0 Implemented
UF0561 # 10 Y:2020 10 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,816 $421 Implemented
UF0561 # 11 Y:2020 11 2020 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $1,418 $5,192 Implemented
UF0561 # 12 Y:2020 12 2020 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $854 $800 Implemented
UF0561 # 13 Y:2020 13 2020 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $624 $0 Implemented
SD0600 # 01 Y:2020 01 2020 REDUCE SCRAP PRODUCTION $80,293 $41,423 Not Implemented
SD0600 # 02 Y:2020 02 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,211 $2,620 Implemented
SD0600 # 03 Y:2020 03 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $869 $450 Implemented
SD0600 # 04 Y:2020 04 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $514 $520 Not Implemented
MI0378 # 01 Y:2020 01 2020 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $12,828 $480 Implemented
MI0378 # 02 Y:2020 02 2020 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,840 $2,673 Not Implemented
MI0378 # 03 Y:2020 03 2020 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM $7,580 $6,182 Not Implemented
MI0378 # 04 Y:2020 04 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,737 $11,160 Implemented
MI0378 # 05 Y:2020 05 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,502 $2,100 Implemented
MI0378 # 06 Y:2020 06 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,909 $1,980 Implemented
MI0378 # 07 Y:2020 07 2020 MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT $1,694 $1,195 Implemented