Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,045
matching recommendationsSIC | 345 | Screw Machine Products, Bolts, Etc. |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0234 # 02 Y:2006 | 02 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $886 | $0 | Not Implemented |
SU0234 # 03 Y:2006 | 03 | 2006 | USE SYNTHETIC LUBRICANT | $118 | $0 | Not Implemented |
SU0234 # 04 Y:2006 | 04 | 2006 | REDUCE VENTILATION AIR | $54,755 | $2,502 | Implemented |
SU0234 # 05 Y:2006 | 05 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,897 | $3,680 | Implemented |
SU0234 # 06 Y:2006 | 06 | 2006 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,746 | $1,114 | Not Implemented |
SU0234 # 07 Y:2006 | 07 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $2,258 | $623 | Implemented |
SU0234 # 08 Y:2006 | 08 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $22,470 | $8,599 | Implemented |
SU0234 # 09 Y:2006 | 09 | 2006 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,901 | $0 | Not Implemented |
SU0234 # 10 Y:2006 | 10 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,801 | $6,762 | Implemented |
SU0234 # 11 Y:2006 | 11 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $41,955 | $48,745 | Implemented |
SU0234 # 12 Y:2006 | 12 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $966 | $1,217 | Not Implemented |
SU0234 # 13 Y:2006 | 13 | 2006 | INSULATE BARE EQUIPMENT | $792 | $1,409 | Implemented |
SU0234 # 14 Y:2006 | 14 | 2006 | INSULATE BARE EQUIPMENT | $579 | $1,245 | Not Implemented |
SU0234 # 15 Y:2006 | 15 | 2006 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $271 | $708 | Not Implemented |
SU0234 # 16 Y:2006 | 16 | 2006 | INSTALL OCCUPANCY SENSORS | $500 | $1,351 | Implemented |
SU0228 # 01 Y:2006 | 01 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,378 | $0 | Implemented |
SU0228 # 02 Y:2006 | 02 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $31,676 | $40,711 | Implemented |
SU0228 # 03 Y:2006 | 03 | 2006 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $39,585 | $111,774 | Implemented |
SU0228 # 04 Y:2006 | 04 | 2006 | INCREASE USE OF AUTOMATION | $1,765,875 | $3,500,000 | Implemented |
MS0287 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,298 | $78,252 | Not Implemented |
MS0287 # 02 Y:2006 | 02 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $17,250 | $41 | Not Implemented |
MS0287 # 03 Y:2006 | 03 | 2006 | CONDENSE OPERATION INTO ONE BUILDING | $9,134 | $100 | Not Implemented |
MS0287 # 04 Y:2006 | 04 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $8,563 | $4,617 | Not Implemented |
MS0287 # 05 Y:2006 | 05 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,562 | $16,090 | Not Implemented |
MS0287 # 06 Y:2006 | 06 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,494 | $3,825 | Not Implemented |