Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
60
matching recommendationsSIC | 345 | Screw Machine Products, Bolts, Etc. |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0349 # 05 Y:2004 | 05 | 2004 | INSULATE BARE EQUIPMENT | $1,332 | $369 | Not Implemented |
SD0349 # 02 Y:2004 | 02 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,934 | $4,300 | Implemented |
SD0349 # 06 Y:2004 | 06 | 2004 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $7,780 | $18,500 | Implemented |
SD0349 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,407 | $3,423 | Implemented |
SD0349 # 01 Y:2004 | 01 | 2004 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $78,560 | $164,000 | Not Implemented |
SD0349 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,757 | $920 | Implemented |
NC0288 # 07 Y:2004 | 07 | 2004 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $6,244 | $18,900 | Not Implemented |
NC0288 # 01 Y:2004 | 01 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,564 | $435 | Implemented |
NC0288 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $239 | $100 | Implemented |
NC0288 # 05 Y:2004 | 05 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,010 | $1,580 | Not Implemented |
NC0288 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $222 | $178 | Not Implemented |
NC0288 # 02 Y:2004 | 02 | 2004 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,570 | $1,725 | Implemented |
NC0288 # 04 Y:2004 | 04 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $15,216 | $3,800 | Implemented |
BD0265 # 05 Y:2004 | 05 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,701 | $1,200 | Not Implemented |
BD0265 # 11 Y:2004 | 11 | 2004 | USE EVAPORATION TO CONCENTRATE MATERIAL | $13,608 | $10,512 | Not Implemented |
BD0265 # 04 Y:2004 | 04 | 2004 | USE SYNTHETIC LUBRICANT | $4,332 | $1,650 | Not Implemented |
BD0265 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,398 | $2,861 | Not Implemented |
BD0265 # 02 Y:2004 | 02 | 2004 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,335 | $20,000 | Not Implemented |
BD0265 # 01 Y:2004 | 01 | 2004 | USE RADIANT HEATER FOR SPOT HEATING | $27,949 | $4,200 | Not Implemented |
BD0265 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,323 | $0 | Not Implemented |
BD0265 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,397 | $2,200 | Not Implemented |
BD0265 # 09 Y:2004 | 09 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $660 | $424 | Not Implemented |
BD0265 # 10 Y:2004 | 10 | 2004 | INSTALL OCCUPANCY SENSORS | $393 | $330 | Not Implemented |
BD0265 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $782 | $602 | Not Implemented |
BD0265 # 12 Y:2004 | 12 | 2004 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $307 | $0 | Not Implemented |