Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
722
matching recommendationsSIC | 3462 | Iron And Steel Forgings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WM0069 # 02 Y:2015 | 02 | 2015 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $30,131 | $24,450 | Implemented |
WM0069 # 03 Y:2015 | 03 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,322 | $95,000 | Not Implemented |
WM0069 # 04 Y:2015 | 04 | 2015 | REPLACE BOILER | $34,455 | $6,500 | Not Implemented |
WM0069 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,294 | $2,400 | Implemented |
WM0069 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $27,723 | $0 | Implemented |
WM0069 # 07 Y:2015 | 07 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,035 | $855 | Not Implemented |
WM0069 # 08 Y:2015 | 08 | 2015 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $6,282 | $14,000 | Not Implemented |
WM0069 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,822 | $6,100 | Implemented |
WM0069 # 10 Y:2015 | 10 | 2015 | INSTALL OCCUPANCY SENSORS | $1,379 | $1,500 | Not Implemented |
WM0069 # 11 Y:2015 | 11 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,423 | $1,600 | Not Implemented |
WV0495 # 01 Y:2014 | 01 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $193,883 | $164,700 | Not Implemented |
WV0495 # 02 Y:2014 | 02 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $51,326 | $26,640 | Not Implemented |
WV0495 # 03 Y:2014 | 03 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,441 | $15,000 | Not Implemented |
WV0495 # 04 Y:2014 | 04 | 2014 | INSTALL SET-BACK TIMERS | $10,203 | $4,200 | Implemented |
WV0495 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,578 | $7,154 | Implemented |
WV0495 # 06 Y:2014 | 06 | 2014 | INSULATE BARE EQUIPMENT | $5,177 | $5,764 | Implemented |
WV0495 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,890 | $5,211 | Implemented |
WV0495 # 08 Y:2014 | 08 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,156 | $725 | Implemented |
WM0004 # 01 Y:2012 | 01 | 2012 | INSULATE BARE EQUIPMENT | $798 | $433 | Implemented |
WM0004 # 02 Y:2012 | 02 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $26,871 | $100,000 | Not Implemented |
WM0004 # 03 Y:2012 | 03 | 2012 | COVER OPEN TANKS | $1,078 | $700 | Not Implemented |
WM0004 # 04 Y:2012 | 04 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,511 | $1,000 | Implemented |
WM0004 # 05 Y:2012 | 05 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,175 | $39,950 | Implemented |
WM0004 # 06 Y:2012 | 06 | 2012 | USE PHOTOCELL CONTROLS | $3,555 | $4,750 | Not Implemented |
WM0004 # 07 Y:2012 | 07 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,280 | $750 | Implemented |