Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsSIC | 347 | Metal Services, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0954 # 07 Y:2020 | 07 | 2020 | INSTALL OCCUPANCY SENSORS | $1,866 | $5,680 | Not Implemented |
GT0954 # 06 Y:2020 | 06 | 2020 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $472 | $1,123 | Implemented |
GT0954 # 05 Y:2020 | 05 | 2020 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,985 | $8,432 | Not Implemented |
GT0954 # 04 Y:2020 | 04 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $326 | $225 | Implemented |
GT0954 # 08 Y:2020 | 08 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $19,391 | $226,091 | Not Implemented |
GT0954 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,911 | $2,747 | Implemented |
GT0954 # 02 Y:2020 | 02 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,031 | $400 | Implemented |
GT0954 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,577 | $1,850 | Implemented |
GT0925 # 01 Y:2019 | 01 | 2019 | INSTALL AUTOMATIC STACK DAMPER | $16,903 | $6,764 | Not Implemented |
GT0925 # 06 Y:2019 | 06 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,358 | $8,787 | Not Implemented |
GT0925 # 05 Y:2019 | 05 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,177 | $2,167 | Implemented |
GT0925 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,266 | $9,527 | Implemented |
GT0925 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,005 | $3,500 | Not Implemented |
GT0925 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,524 | $1,100 | Implemented |
GT0774 # 07 Y:2003 | 07 | 2003 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $27,072 | $3,660 | Not Implemented |
GT0774 # 06 Y:2003 | 06 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $290 | $200 | Implemented |
GT0774 # 05 Y:2003 | 05 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $904 | $1,549 | Implemented |
GT0774 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $164 | $300 | Not Implemented |
GT0774 # 03 Y:2003 | 03 | 2003 | INCREASE AMOUNT OF CONDENSATE RETURNED | $7,977 | $2,500 | Implemented |
GT0774 # 02 Y:2003 | 02 | 2003 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $1,135 | $2,700 | Not Implemented |
GT0774 # 01 Y:2003 | 01 | 2003 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $8,200 | $0 | Implemented |
GT0770 # 01 Y:2003 | 01 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $490 | $0 | Implemented |
GT0770 # 05 Y:2003 | 05 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,380 | $0 | Implemented |
GT0770 # 04 Y:2003 | 04 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,276 | $2,600 | Not Implemented |
GT0770 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $109 | $287 | Implemented |