IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

107

matching recommendations
Reset
SIC 349 Misc. Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MS0299 # 05 Y:2006 05 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,496 $4,275 Implemented
MS0299 # 04 Y:2006 04 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,779 $231 Implemented
AS0423 # 02 Y:2006 02 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $13,786 $1,000 n/a
AS0423 # 03 Y:2006 03 2006 REDESIGN FLOW TO MINIMIZE MASS TRANSFER LENGTH $13,786 $13,000 n/a
AS0423 # 04 Y:2006 04 2006 UPGRADE CONTROLS ON COMPRESSORS $13,316 $10,000 n/a
AS0423 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,912 $10,000 n/a
AS0423 # 01 Y:2006 01 2006 $205,767 $2,100,000 n/a
AS0423 # 06 Y:2006 06 2006 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $8,401 $16,000 n/a
OK0728 # 06 Y:2006 06 2006 AIR CONDITION ONLY SPACE NECESSARY $6,517 $2,295 Not Implemented
OK0728 # 07 Y:2006 07 2006 $2,500 $0 Not Implemented
OK0728 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $506 $430 Not Implemented
OK0728 # 04 Y:2006 04 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $5,034 $1,994 Not Implemented
OK0728 # 03 Y:2006 03 2006 RECOVER WASTE HEAT FROM EQUIPMENT $8,567 $34,652 Not Implemented
OK0728 # 02 Y:2006 02 2006 RECOVER WASTE HEAT FROM EQUIPMENT $75,048 $240,000 Not Implemented
OK0728 # 01 Y:2006 01 2006 REDUCE VENTILATION AIR $35,971 $12,184 Not Implemented
UD0739 # 10 Y:2006 10 2006 SHUT OFF PILOTS IN STANDBY EQUIPMENT $109 $0 Implemented
UD0739 # 11 Y:2006 11 2006 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $104 $0 Implemented
UD0739 # 08 Y:2006 08 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $600 $0 Implemented
UD0739 # 07 Y:2006 07 2006 UPGRADE CONTROLS ON COMPRESSORS $873 $1,900 Not Implemented
UD0739 # 09 Y:2006 09 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $539 $540 Not Implemented
UD0739 # 06 Y:2006 06 2006 UPGRADE CONTROLS ON COMPRESSORS $1,049 $387 Implemented
UD0739 # 02 Y:2006 02 2006 INSTALL TIMERS AND/OR THERMOSTATS $11,417 $3,300 Not Implemented
UD0739 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,822 $23,400 Not Implemented
UD0739 # 01 Y:2006 01 2006 $41,626 $4,000 Implemented
UD0739 # 05 Y:2006 05 2006 $1,391 $30 Implemented