Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
220
matching recommendationsSIC | 3491 | Industrial Valves |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0131 # 04 Y:1998 | 04 | 1998 | USE SYNTHETIC LUBRICANT | $179 | $336 | Implemented |
WV0131 # 08 Y:1998 | 08 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $262 | $620 | Implemented |
WV0131 # 09 Y:1998 | 09 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,780 | $5,000 | Implemented |
AM0308 # 01 Y:1997 | 01 | 1997 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $39,645 | $4,200 | Implemented |
AM0308 # 02 Y:1997 | 02 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $6,870 | $0 | Implemented |
AM0308 # 05 Y:1997 | 05 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,790 | $675 | Implemented |
AM0308 # 06 Y:1997 | 06 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,505 | $50 | Implemented |
AM0308 # 08 Y:1997 | 08 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $850 | $1,960 | Implemented |
AM0308 # 09 Y:1997 | 09 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $785 | $150 | Implemented |
AM0308 # 10 Y:1997 | 10 | 1997 | INSTALL SKYLIGHTS | $20,665 | $9,300 | Implemented |
NC0124 # 01 Y:1997 | 01 | 1997 | AIR CONDITION ONLY SPACE NECESSARY | $9,590 | $3,000 | Implemented |
NC0124 # 05 Y:1997 | 05 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $790 | $270 | Implemented |
NC0124 # 07 Y:1997 | 07 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,913 | $6,240 | Implemented |
NC0124 # 08 Y:1997 | 08 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,572 | $2,000 | Implemented |
NC0124 # 10 Y:1997 | 10 | 1997 | IMPLEMENT A MACHINE AND COOLANT SUMP CLEANING PROGRAM TO MINIMIZE COOLANT CONTAMINATION | $7,405 | $0 | Implemented |
NC0124 # 11 Y:1997 | 11 | 1997 | USE REVERSE OSMOSIS TO CONCENTRATE MATERIAL | $2,755 | $2,830 | Implemented |
NC0124 # 14 Y:1997 | 14 | 1997 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $12,000 | $8,500 | Implemented |
NC0124 # 15 Y:1997 | 15 | 1997 | INSTALL MAGAZINES FOR TEMPORARY STORAGE | $92,400 | $35,000 | Implemented |
AM0300 # 03 Y:1997 | 03 | 1997 | USE A RAG RECYCLE SERVICE | $780 | $60 | Implemented |
AM0300 # 04 Y:1997 | 04 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $530 | $220 | Implemented |
AS0188 # 01 Y:1996 | 01 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $11,373 | $21,500 | Implemented |
AS0188 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,900 | $13,282 | Implemented |
AS0188 # 04 Y:1996 | 04 | 1996 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,409 | $9,450 | Implemented |
AS0188 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,780 | $17,184 | Implemented |
AS0188 # 07 Y:1996 | 07 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $280 | $450 | Implemented |