IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

382

matching recommendations
Reset
SIC 3492 Fluid Power Valves & Hose Fittings
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0474 # 05 Y:2016 05 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,746 $400 Implemented
BD0474 # 06 Y:2016 06 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,446 $563 Implemented
BD0474 # 07 Y:2016 07 2016 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,390 $50 Not Implemented
BD0474 # 08 Y:2016 08 2016 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,294 $2,500 Not Implemented
BD0474 # 09 Y:2016 09 2016 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,161 $50 Not Implemented
BD0474 # 10 Y:2016 10 2016 RECOVER WASTE HEAT FROM EQUIPMENT $963 $3,000 Not Implemented
MI0286 # 01 Y:2015 01 2015 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $19,094 $29,862 Implemented
MI0286 # 02 Y:2015 02 2015 LOWER CEILING TO REDUCE CONDITIONED SPACE $14,710 $100,350 Implemented
MI0286 # 03 Y:2015 03 2015 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $12,602 $80 Not Implemented
MI0286 # 04 Y:2015 04 2015 RECOVER WASTE HEAT FROM EQUIPMENT $7,447 $6,660 Not Implemented
MI0286 # 05 Y:2015 05 2015 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $5,778 $4,691 Not Implemented
MI0286 # 06 Y:2015 06 2015 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE $3,819 $11,872 Not Implemented
MI0286 # 07 Y:2015 07 2015 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $3,433 $5,370 Not Implemented
MI0286 # 08 Y:2015 08 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,382 $40 Not Implemented
MI0286 # 09 Y:2015 09 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $920 $1,670 Not Implemented
MI0285 # 07 Y:2015 07 2015 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,621 $5,370 Not Implemented
MI0285 # 06 Y:2015 06 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,096 $1,660 Not Implemented
MI0285 # 05 Y:2015 05 2015 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $8,325 $4,691 Not Implemented
MI0285 # 04 Y:2015 04 2015 LOWER CEILING TO REDUCE CONDITIONED SPACE $13,892 $76,650 Implemented
MI0285 # 03 Y:2015 03 2015 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $15,400 $80 Implemented
MI0285 # 02 Y:2015 02 2015 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $22,640 $52,920 Implemented
MI0285 # 01 Y:2015 01 2015 COVER OPEN TANKS $36,126 $25,100 Not Implemented
MI0285 # 08 Y:2015 08 2015 RECOVER WASTE HEAT FROM EQUIPMENT $3,310 $6,660 Not Implemented
MI0285 # 09 Y:2015 09 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,010 $40 Not Implemented
MI0284 # 08 Y:2015 08 2015 INSTALL OCCUPANCY SENSORS $207 $105 Not Implemented