Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
48
matching recommendationsSIC | 3496 | Misc. Fabricated Wire Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0132 # 02 Y:1991 | 02 | 1991 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $20,700 | $78,000 | Not Implemented |
AM0132 # 03 Y:1991 | 03 | 1991 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,300 | $0 | Not Implemented |
AM0132 # 04 Y:1991 | 04 | 1991 | PAY UTILITY BILLS ON TIME | $1,315 | $0 | Not Implemented |
AM0132 # 05 Y:1991 | 05 | 1991 | IMPROVE LUBRICATION PRACTICES | $704 | $0 | Not Implemented |
AM0132 # 06 Y:1991 | 06 | 1991 | INSTALL SET-BACK TIMERS | $150 | $0 | Not Implemented |
AM0132 # 07 Y:1991 | 07 | 1991 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $130 | $0 | Not Implemented |
AM0132 # 01 Y:1991 | 01 | 1991 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $20,900 | $78,000 | Not Implemented |
UF0013 # 01 Y:1991 | 01 | 1991 | OPTIMIZE PLANT POWER FACTOR | $27,648 | $34,850 | Implemented |
UF0013 # 10 Y:1991 | 10 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,713 | $20,700 | Implemented |
UF0013 # 02 Y:1991 | 02 | 1991 | USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS | $18,637 | $34,000 | Implemented |
UF0013 # 03 Y:1991 | 03 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,117 | $0 | Implemented |
UF0013 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,964 | $0 | Implemented |
UF0013 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,775 | $21,477 | Implemented |
UF0013 # 06 Y:1991 | 06 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $6,364 | $0 | Implemented |
UF0013 # 07 Y:1991 | 07 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,089 | $1,892 | Implemented |
UF0013 # 08 Y:1991 | 08 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,841 | $3,067 | Implemented |
UF0013 # 09 Y:1991 | 09 | 1991 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $756 | $880 | Implemented |
GT0446 # 01 Y:1991 | 01 | 1991 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $15,430 | $0 | Implemented |
GT0446 # 02 Y:1991 | 02 | 1991 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $439 | $140 | Implemented |
GT0446 # 03 Y:1991 | 03 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,377 | $0 | Implemented |
GT0446 # 04 Y:1991 | 04 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $120 | $30 | Implemented |
GT0446 # 07 Y:1991 | 07 | 1991 | COVER OPEN TANKS | $9,880 | $7,550 | Implemented |
GT0446 # 06 Y:1991 | 06 | 1991 | INSTALL / REPAIR INSULATION ON STEAM LINES | $80 | $130 | Implemented |
GT0446 # 05 Y:1991 | 05 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $18,000 | $300 | Implemented |
TN0435 # 05 Y:1991 | 05 | 1991 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $892 | $190 | Implemented |