IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

29

matching recommendations
Reset
SIC 3498 Fabricated Pipe And Fittings
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CI0021 # 02 Y:2023 02 2023 UPGRADE CONTROLS ON COMPRESSORS $10,578 $2,500 n/a
CI0021 # 01 Y:2023 01 2023 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $13,010 $43,210 n/a
CI0021 # 08 Y:2023 08 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,149 $500 n/a
CI0021 # 07 Y:2023 07 2023 INSTALL OCCUPANCY SENSORS $2,177 $2,500 n/a
CI0021 # 06 Y:2023 06 2023 TURN OFF EQUIPMENT WHEN NOT IN USE $3,548 $0 n/a
CI0021 # 05 Y:2023 05 2023 USE PHOTOCELL CONTROLS $3,983 $2,500 n/a
CI0021 # 04 Y:2023 04 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,563 $3,850 n/a
CI0021 # 03 Y:2023 03 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,619 $300 n/a
LM0064 # 10 Y:2003 10 2003 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $144,153 $2,500 Not Implemented
LM0064 # 09 Y:2003 09 2003 DEVELOP STANDARD OPERATING PROCEDURES $123,760 $56,040 n/a
LM0064 # 08 Y:2003 08 2003 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $13,674 $300 Not Implemented
LM0064 # 07 Y:2003 07 2003 ELIMINATE LEAKS IN COMBUSTIBLE GAS LINES $453 $400 Implemented
LM0064 # 06 Y:2003 06 2003 INSTALL SPECTRAL REFLECTORS / DELAMP $2,520 $0 Implemented
LM0064 # 05 Y:2003 05 2003 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $9,529 $0 Not Implemented
LM0064 # 04 Y:2003 04 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $16,099 $9,475 Implemented
LM0064 # 03 Y:2003 03 2003 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $4,321 $200 Implemented
LM0064 # 02 Y:2003 02 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $76,727 $9,000 n/a
LM0064 # 01 Y:2003 01 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,721 $320 Implemented
LM0064 # 11 Y:2003 11 2003 CROSS-TRAIN PERSONNEL TO AVOID LOST TIME $360,180 $118,080 Implemented
LM0064 # 12 Y:2003 12 2003 MODIFY CURRENT INCENTIVE PROGRAM $34,000 $5,000 Implemented
LM0064 # 13 Y:2003 13 2003 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES $84,000 $1,000 Not Implemented
LM0040 # 06 Y:2002 06 2002 MAINTAIN CLEAN CONDITIONS BEFORE PAINTING $108,300 $200 Not Implemented
LM0040 # 05 Y:2002 05 2002 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $4,888 $9,000 Not Implemented
LM0040 # 04 Y:2002 04 2002 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $2,360 $1,440 Not Implemented
LM0040 # 03 Y:2002 03 2002 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,476 $288 Implemented