IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

967

matching recommendations
Reset
SIC 3499 Fabricated Metal Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MZ0062 # 01 Y:2011 01 2011 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $7,242 $1,160 Implemented
MZ0062 # 02 Y:2011 02 2011 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $31,772 $49,280 Implemented
MZ0062 # 04 Y:2011 04 2011 INSTALL SPECTRAL REFLECTORS / DELAMP $1,360 $100 Implemented
MZ0062 # 07 Y:2011 07 2011 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $26,441 $1,300 Implemented
MZ0062 # 08 Y:2011 08 2011 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $8,105 $15,000 Implemented
MZ0062 # 09 Y:2011 09 2011 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,053 $9,000 Implemented
MZ0062 # 11 Y:2011 11 2011 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $17,836 $10,000 Implemented
MZ0062 # 13 Y:2011 13 2011 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $91 $300 Implemented
MZ0062 # 14 Y:2011 14 2011 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $11,657 $150,000 Implemented
MZ0062 # 16 Y:2011 16 2011 UPGRADE CONTROLS ON COMPRESSORS $11,500 $18,000 Implemented
UD0823 # 06 Y:2010 06 2010 INSTALL OCCUPANCY SENSORS $17,201 $7,375 Implemented
UD0823 # 08 Y:2010 08 2010 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,268 $25 Implemented
UD0823 # 10 Y:2010 10 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $524 $25 Implemented
UD0823 # 13 Y:2010 13 2010 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $10,010 $50,050 Implemented
UD0823 # 15 Y:2010 15 2010 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $355 $25 Implemented
OK0782 # 01 Y:2009 01 2009 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $852 $354 Implemented
OK0782 # 03 Y:2009 03 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,733 $0 Implemented
OK0782 # 07 Y:2009 07 2009 INSTALL / REPAIR INSULATION ON STEAM LINES $4,815 $820 Implemented
OK0782 # 08 Y:2009 08 2009 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS $700 $1,825 Implemented
UW0032 # 02 Y:2009 02 2009 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $8,782 $31,747 Implemented
UW0032 # 03 Y:2009 03 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,643 $10,000 Implemented
UW0032 # 04 Y:2009 04 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,065 $3,070 Implemented
UW0032 # 05 Y:2009 05 2009 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $297 $200 Implemented
UD0802 # 02 Y:2009 02 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,384 $29,087 Implemented
UD0802 # 03 Y:2009 03 2009 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $7,645 $0 Implemented