Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
83
matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0514 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,774 | $3,179 | Not Implemented |
SU0514 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46 | $49 | Not Implemented |
SU0514 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,008 | $0 | Not Implemented |
SU0514 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,219 | $1,953 | Not Implemented |
SU0514 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $18,996 | $9,943 | Not Implemented |
SU0514 # 02 Y:2022 | 02 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $22,430 | $675 | Not Implemented |
LE0497 # 03 Y:2020 | 03 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $21,231 | $32,000 | Not Implemented |
LE0497 # 06 Y:2020 | 06 | 2020 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $3,520 | $13,000 | Not Implemented |
LE0497 # 05 Y:2020 | 05 | 2020 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $1,765 | $4,600 | Not Implemented |
LE0497 # 04 Y:2020 | 04 | 2020 | LOWER COMPRESSOR PRESSURE THROUGH A/C SYSTEM MODIFICATION | $2,905 | $5,000 | Not Implemented |
LE0497 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $13,727 | $10,000 | Not Implemented |
LE0497 # 01 Y:2020 | 01 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,793 | $4,200 | Not Implemented |
SU0438 # 06 Y:2017 | 06 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,174 | $3,708 | Implemented |
SU0438 # 01 Y:2017 | 01 | 2017 | ELIMINATE/REDUCE AN OPERATION | $4,956 | $2,304 | Not Implemented |
SU0438 # 02 Y:2017 | 02 | 2017 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $467 | $936 | Implemented |
SU0438 # 05 Y:2017 | 05 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $169 | $416 | Not Implemented |
SU0438 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $59 | $66 | Implemented |
SU0438 # 04 Y:2017 | 04 | 2017 | REDUCE VENTILATION AIR | $449 | $600 | Implemented |
SU0331 # 05 Y:2013 | 05 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $142 | $299 | Implemented |
SU0331 # 01 Y:2013 | 01 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $808 | $0 | Implemented |
SU0331 # 04 Y:2013 | 04 | 2013 | INSTALL SET-BACK TIMERS | $299 | $228 | Implemented |
SU0331 # 03 Y:2013 | 03 | 2013 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $19 | $0 | Implemented |
SU0331 # 06 Y:2013 | 06 | 2013 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $188 | $384 | Not Implemented |
SU0331 # 02 Y:2013 | 02 | 2013 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $211 | $0 | Implemented |
SU0266 # 09 Y:2008 | 09 | 2008 | INSTALL OCCUPANCY SENSORS | $100 | $626 | Not Implemented |