IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

94

matching recommendations
Reset
SIC 3499 Fabricated Metal Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UM0425 # 02 Y:2013 02 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,480 $3,300 Implemented
UM0425 # 01 Y:2013 01 2013 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $9,900 $13,000 Not Implemented
UM0425 # 03 Y:2013 03 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,115 $0 Implemented
UM0425 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $695 $308 Implemented
UM0425 # 04 Y:2013 04 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,752 $5,000 Implemented
UM0400 # 07 Y:2012 07 2012 RECOVER WASTE HEAT FROM EQUIPMENT $3,660 $4,000 Not Implemented
UM0400 # 04 Y:2012 04 2012 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,410 $200 Not Implemented
UM0400 # 03 Y:2012 03 2012 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $5,437 $4,000 Not Implemented
UM0400 # 01 Y:2012 01 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $38,282 $47,885 Not Implemented
UM0400 # 06 Y:2012 06 2012 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $706 $10 Not Implemented
UM0400 # 02 Y:2012 02 2012 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $15,755 $17,500 Not Implemented
UM0400 # 05 Y:2012 05 2012 INSTALL OCCUPANCY SENSORS $3,287 $5,040 Not Implemented
UM0400 # 08 Y:2012 08 2012 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING $1,447 $4,000 Not Implemented
UM0373 # 06 Y:2010 06 2010 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,651 $6,300 Not Implemented
UM0373 # 02 Y:2010 02 2010 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,961 $200 Not Implemented
UM0373 # 03 Y:2010 03 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,127 $4,000 Not Implemented
UM0373 # 01 Y:2010 01 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $20,156 $44,196 Not Implemented
UM0373 # 05 Y:2010 05 2010 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $5,428 $1,040 Not Implemented
UM0373 # 04 Y:2010 04 2010 INSTALL OCCUPANCY SENSORS $870 $828 Not Implemented
IC0147 # 02 Y:2008 02 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $35,889 $55,200 Implemented
IC0147 # 05 Y:2008 05 2008 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE $395 $250 Implemented
IC0147 # 06 Y:2008 06 2008 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $24,605 $0 Implemented
IC0147 # 11 Y:2008 11 2008 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $6,598 $9,911 Implemented
IC0147 # 12 Y:2008 12 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,138 $1,380 Implemented
IC0147 # 13 Y:2008 13 2008 UPGRADE OBSOLETE EQUIPMENT $17,075 $5,520 Implemented