Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

213

matching recommendations
Reset
SIC 3499 Fabricated Metal Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0802 # 08 Y:2009 08 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $797 $1,907 Implemented
UD0802 # 09 Y:2009 09 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $487 $2,374 Implemented
UD0802 # 10 Y:2009 10 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,334 $1,000 Implemented
UD0802 # 11 Y:2009 11 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $194 $0 Not Implemented
UD0739 # 01 Y:2006 01 2006 CHANGE OPERATING CONDITIONS $41,626 $4,000 Implemented
UD0739 # 02 Y:2006 02 2006 INSTALL TIMERS AND/OR THERMOSTATS $11,417 $3,300 Not Implemented
UD0739 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,822 $23,400 Not Implemented
UD0739 # 04 Y:2006 04 2006 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE $3,397 $0 Implemented
UD0739 # 05 Y:2006 05 2006 CONDENSE OPERATION INTO ONE BUILDING $1,391 $30 Implemented
UD0739 # 06 Y:2006 06 2006 UPGRADE CONTROLS ON COMPRESSORS $1,049 $387 Implemented
UD0739 # 07 Y:2006 07 2006 UPGRADE CONTROLS ON COMPRESSORS $873 $1,900 Not Implemented
UD0739 # 08 Y:2006 08 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $600 $0 Implemented
UD0739 # 09 Y:2006 09 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $539 $540 Not Implemented
UD0739 # 10 Y:2006 10 2006 SHUT OFF PILOTS IN STANDBY EQUIPMENT $109 $0 Implemented
UD0739 # 11 Y:2006 11 2006 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $104 $0 Implemented
UD0714 # 01 Y:2005 01 2005 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $14,094 $5,000 Not Implemented
UD0714 # 02 Y:2005 02 2005 INSTALL EQUIPMENT TO MOVE PRODUCT $13,500 $10,000 Not Implemented
UD0714 # 03 Y:2005 03 2005 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES $12,150 $1,000 Implemented
UD0714 # 04 Y:2005 04 2005 USE MINIMUM SAFE OVEN VENTILATION $6,825 $3,000 Implemented
UD0714 # 05 Y:2005 05 2005 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $4,482 $2,000 Not Implemented
UD0714 # 06 Y:2005 06 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,427 $14,204 Not Implemented
UD0714 # 07 Y:2005 07 2005 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $2,772 $165 Implemented
UD0714 # 08 Y:2005 08 2005 USE MINIMUM SAFE OVEN VENTILATION $1,972 $150 Implemented
UD0714 # 09 Y:2005 09 2005 MINIMIZE WATER USAGE $1,311 $1,200 Implemented
UD0714 # 10 Y:2005 10 2005 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,296 $0 Implemented