Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,117
matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CW0123 # 04 Y:2022 | 04 | 2022 | IMPROVE LUBRICATION PRACTICES | $27,999 | $8,008 | n/a |
CW0123 # 05 Y:2022 | 05 | 2022 | USE OPTIMUM TEMPERATURE | $4,521 | $3,500 | n/a |
CW0123 # 06 Y:2022 | 06 | 2022 | SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS | $2,357 | $0 | n/a |
CW0123 # 07 Y:2022 | 07 | 2022 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $30,793 | $45,000 | n/a |
CW0123 # 08 Y:2022 | 08 | 2022 | RELOCATE OVEN / FURNACE TO MORE EFFICIENT LOCATION | $7,698 | $5,000 | n/a |
CW0123 # 09 Y:2022 | 09 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,158 | $12,694 | n/a |
CW0123 # 10 Y:2022 | 10 | 2022 | USE POWER DURING OFF-PEAK PERIODS | $1,949 | $0 | n/a |
OR0751 # 01 Y:2022 | 01 | 2022 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $12,526 | $140 | Not Implemented |
OR0751 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,956 | $1,175 | Not Implemented |
OR0751 # 03 Y:2022 | 03 | 2022 | FILTER AND REUSE HYDRAULIC OIL | $74,774 | $48,589 | Not Implemented |
OR0751 # 04 Y:2022 | 04 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,125 | $1,272 | Not Implemented |
TT0269 # 01 Y:2022 | 01 | 2022 | CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES | $24,682 | $2,000 | Not Implemented |
TT0269 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,069 | $25,000 | Not Implemented |
TT0269 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $6,223 | $27,500 | Not Implemented |
TT0269 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,847 | $3,500 | Not Implemented |
TT0269 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,648 | $2,500 | Not Implemented |
TT0269 # 06 Y:2022 | 06 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,911 | $11,000 | Not Implemented |
WV0618 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $354 | $90 | Implemented |
WV0618 # 06 Y:2022 | 06 | 2022 | DEVELOP A REPAIR/REPLACE POLICY | $369 | $1,670 | Implemented |
WV0618 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,089 | $525 | Implemented |
WV0618 # 04 Y:2022 | 04 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $1,409 | $3,970 | Not Implemented |
WV0618 # 03 Y:2022 | 03 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,452 | $1,125 | Implemented |
WV0618 # 02 Y:2022 | 02 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,969 | $4,600 | Not Implemented |
WV0618 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,096 | $10,131 | Not Implemented |
DL0200 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $16,029 | $0 | Not Implemented |