Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
144
matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SJ0002 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $424 | $194 | Implemented |
SJ0002 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,309 | $22,700 | Implemented |
SJ0002 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,772 | $0 | Implemented |
SJ0002 # 04 Y:2023 | 04 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,185 | $0 | Implemented |
SJ0002 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,741 | $652 | Implemented |
SJ0002 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $72,623 | $275,269 | Not Implemented |
SD0598 # 02 Y:2020 | 02 | 2020 | INSTALL OCCUPANCY SENSORS | $868 | $693 | Not Implemented |
SD0598 # 04 Y:2020 | 04 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $243 | $0 | Implemented |
SD0598 # 01 Y:2020 | 01 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,874 | $2,784 | Not Implemented |
SD0598 # 03 Y:2020 | 03 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $688 | $150 | Implemented |
SF0548 # 07 Y:2019 | 07 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,924 | $172,115 | Implemented |
SF0548 # 03 Y:2019 | 03 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $473 | $100 | Implemented |
SF0548 # 02 Y:2019 | 02 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $193 | $0 | Implemented |
SF0548 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,363 | $300 | Implemented |
SF0548 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,047 | $2,930 | Implemented |
SF0548 # 05 Y:2019 | 05 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,653 | $1,103 | Implemented |
SF0548 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,764 | $0 | Implemented |
SD0547 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,165 | $1,500 | Implemented |
SD0547 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,853 | $20,582 | Implemented |
SD0547 # 07 Y:2017 | 07 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $689 | $567 | Implemented |
SD0547 # 04 Y:2017 | 04 | 2017 | INSTALL OCCUPANCY SENSORS | $1,746 | $2,045 | Not Implemented |
SD0547 # 02 Y:2017 | 02 | 2017 | USE PHOTOCELL CONTROLS | $3,679 | $11,568 | Implemented |
SD0547 # 06 Y:2017 | 06 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $725 | $914 | Not Implemented |
SD0547 # 05 Y:2017 | 05 | 2017 | INSULATE BARE EQUIPMENT | $1,326 | $750 | Implemented |
SD0484 # 04 Y:2014 | 04 | 2014 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $6,896 | $400 | Implemented |