Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
53
matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0306 # 02 Y:2024 | 02 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,348 | $0 | n/a |
TT0306 # 10 Y:2024 | 10 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $494 | $1,400 | n/a |
TT0306 # 08 Y:2024 | 08 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $819 | $785 | n/a |
TT0306 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $828 | $840 | n/a |
TT0306 # 06 Y:2024 | 06 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $917 | $113 | n/a |
TT0306 # 05 Y:2024 | 05 | 2024 | INSTALL OCCUPANCY SENSORS | $1,321 | $1,560 | n/a |
TT0306 # 04 Y:2024 | 04 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $3,347 | $2,600 | n/a |
TT0306 # 03 Y:2024 | 03 | 2024 | TREAT AND REUSE RINSE WATERS | $3,460 | $1,590 | n/a |
TT0306 # 01 Y:2024 | 01 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,784 | $3,840 | n/a |
TT0306 # 09 Y:2024 | 09 | 2024 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $650 | $100 | n/a |
TT0269 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $6,223 | $27,500 | Not Implemented |
TT0269 # 06 Y:2022 | 06 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,911 | $11,000 | Not Implemented |
TT0269 # 04 Y:2022 | 04 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,847 | $3,500 | Not Implemented |
TT0269 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,069 | $25,000 | Not Implemented |
TT0269 # 01 Y:2022 | 01 | 2022 | CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES | $24,682 | $2,000 | Not Implemented |
TT0269 # 05 Y:2022 | 05 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,648 | $2,500 | Not Implemented |
TT0079 # 08 Y:2011 | 08 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,584 | $0 | Not Implemented |
TT0079 # 07 Y:2011 | 07 | 2011 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $5,691 | $0 | Not Implemented |
TT0079 # 01 Y:2011 | 01 | 2011 | DISCONNECT BALLASTS | $508 | $0 | Implemented |
TT0079 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $205 | $0 | Implemented |
TT0079 # 06 Y:2011 | 06 | 2011 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,937 | $0 | Implemented |
TT0079 # 05 Y:2011 | 05 | 2011 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $631 | $0 | Not Implemented |
TT0079 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $1,618 | $0 | Not Implemented |
TT0079 # 02 Y:2011 | 02 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $336 | $0 | Implemented |
TT0001 # 10 Y:2007 | 10 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,038 | $0 | Not Implemented |