IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

27

matching recommendations
Reset
SIC 3499 Fabricated Metal Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
NC0386 # 08 Y:2009 08 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,405 $32,776 Not Implemented
NC0386 # 07 Y:2009 07 2009 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,493 $6,490 Not Implemented
NC0386 # 06 Y:2009 06 2009 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $1,520 $0 Not Implemented
NC0386 # 05 Y:2009 05 2009 DEVELOP A REPAIR/REPLACE POLICY $2,916 $2,848 Not Implemented
NC0386 # 04 Y:2009 04 2009 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,236 $100 Not Implemented
NC0386 # 03 Y:2009 03 2009 RECOVER WASTE HEAT FROM EQUIPMENT $9,621 $3,300 Not Implemented
NC0386 # 02 Y:2009 02 2009 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $6,160 $0 Not Implemented
NC0386 # 01 Y:2009 01 2009 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $31,742 $49,000 Not Implemented
NC0386 # 09 Y:2009 09 2009 INSTALL OCCUPANCY SENSORS $6,974 $8,400 Not Implemented
NC0365 # 02 Y:2007 02 2007 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $11,898 $7,000 Implemented
NC0365 # 06 Y:2007 06 2007 OPTIMIZE PLANT POWER FACTOR $6,133 $12,000 Implemented
NC0365 # 05 Y:2007 05 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,788 $50 Implemented
NC0365 # 04 Y:2007 04 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $24,833 $71,577 Not Implemented
NC0365 # 03 Y:2007 03 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,542 $100 Implemented
NC0365 # 01 Y:2007 01 2007 REDUCE VENTILATION AIR $11,968 $28,000 Implemented
NC0123 # 01 Y:1997 01 1997 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,987 $0 Implemented
NC0123 # 11 Y:1997 11 1997 $10,775 $0 Implemented
NC0123 # 10 Y:1997 10 1997 CONTRACT A WOOD PALLET RECYCLING COMPANY $375 $200 Implemented
NC0123 # 09 Y:1997 09 1997 REDUCE SCRAP PRODUCTION $3,429 $15,000 Not Implemented
NC0123 # 08 Y:1997 08 1997 USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS $14,528 $12,000 Not Implemented
NC0123 # 07 Y:1997 07 1997 REDUCE WATER USE WITH COUNTER CURRENT RINSING $926 $200 Not Implemented
NC0123 # 06 Y:1997 06 1997 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $7,282 $14,319 Not Implemented
NC0123 # 05 Y:1997 05 1997 UPGRADE CONTROLS ON COMPRESSORS $376 $400 Not Implemented
NC0123 # 04 Y:1997 04 1997 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $126 $25 Not Implemented
NC0123 # 03 Y:1997 03 1997 ADD AREA LIGHTING SWITCHES $1,475 $2,000 Not Implemented