Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0121 # 03 Y:1991 | 03 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $465 | $500 | Implemented |
OR0121 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $122 | $120 | Implemented |
OR0121 # 05 Y:1991 | 05 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $174 | $519 | Implemented |
OR0121 # 06 Y:1991 | 06 | 1991 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $336 | $1,000 | Implemented |
OR0121 # 07 Y:1991 | 07 | 1991 | USE RADIANT HEATER FOR SPOT HEATING | $2,839 | $12,320 | Implemented |
SD0008 # 01 Y:1991 | 01 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $170 | $190 | Implemented |
SD0008 # 02 Y:1991 | 02 | 1991 | RECOVER WASTE HEAT FROM EQUIPMENT | $513 | $600 | Implemented |
SD0008 # 03 Y:1991 | 03 | 1991 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $492 | $120 | Implemented |
SD0008 # 04 Y:1991 | 04 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,281 | $3,150 | Implemented |
SD0008 # 05 Y:1991 | 05 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $1,113 | $2,940 | Implemented |
SD0008 # 06 Y:1991 | 06 | 1991 | KEEP LAMPS AND REFLECTORS CLEAN | $4,128 | $13,356 | Implemented |
SD0008 # 07 Y:1991 | 07 | 1991 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $4,016 | $9,150 | Implemented |
SD0008 # 08 Y:1991 | 08 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,430 | $2,080 | Implemented |
SD0008 # 09 Y:1991 | 09 | 1991 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $3,497 | $9,900 | Implemented |
UF0010 # 01 Y:1991 | 01 | 1991 | INSTALL SPECTRAL REFLECTORS / DELAMP | $5,576 | $2,795 | Implemented |
UF0010 # 02 Y:1991 | 02 | 1991 | INSTALL SET-BACK TIMERS | $185 | $192 | Implemented |
UF0010 # 03 Y:1991 | 03 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $121 | $149 | Implemented |
UF0010 # 04 Y:1991 | 04 | 1991 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,610 | $0 | Implemented |
UF0010 # 05 Y:1991 | 05 | 1991 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $158 | $176 | Implemented |
UF0010 # 06 Y:1991 | 06 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $85 | $300 | Implemented |
KU0350 # 01 Y:1991 | 01 | 1991 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $36,079 | $0 | Implemented |
KU0350 # 02 Y:1991 | 02 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,101 | $12,000 | Implemented |
KU0350 # 03 Y:1991 | 03 | 1991 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,192 | $7,440 | Implemented |
KU0350 # 04 Y:1991 | 04 | 1991 | INSTALL SET-BACK TIMERS | $995 | $550 | Implemented |
KU0350 # 05 Y:1991 | 05 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $550 | $950 | Implemented |