Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0696 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,810 | $28,220 | Implemented |
AM0696 # 05 Y:2015 | 05 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $870 | $0 | Implemented |
AM0696 # 07 Y:2015 | 07 | 2015 | INSTALL OCCUPANCY SENSORS | $280 | $630 | Implemented |
AM0696 # 08 Y:2015 | 08 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $130 | $0 | Implemented |
SU0402 # 03 Y:2015 | 03 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,073 | $600 | Implemented |
SU0402 # 05 Y:2015 | 05 | 2015 | REDUCE VENTILATION AIR | $8,182 | $2,941 | Implemented |
SU0402 # 07 Y:2015 | 07 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $770 | $950 | Implemented |
SU0402 # 08 Y:2015 | 08 | 2015 | LOWER CEILING TO REDUCE CONDITIONED SPACE | $1,495 | $2,000 | Implemented |
SU0402 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $431 | $560 | Implemented |
SU0402 # 10 Y:2015 | 10 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $7,911 | $23,244 | Implemented |
MZ0205 # 02 Y:2015 | 02 | 2015 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $1,559 | $0 | Implemented |
MZ0205 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,581 | $850 | Implemented |
MZ0205 # 04 Y:2015 | 04 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $397 | $0 | Implemented |
MZ0205 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $969 | $400 | Implemented |
BS0069 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $99 | $576 | Implemented |
BS0069 # 03 Y:2015 | 03 | 2015 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $879 | $503 | Implemented |
BS0069 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $1,145 | Implemented |
BS0069 # 05 Y:2015 | 05 | 2015 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $198 | $374 | Implemented |
SU0400 # 03 Y:2015 | 03 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $325 | $0 | Implemented |
SU0400 # 04 Y:2015 | 04 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $36 | $0 | Implemented |
SU0400 # 06 Y:2015 | 06 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $1,555 | $1,247 | Implemented |
SU0400 # 08 Y:2015 | 08 | 2015 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $5,273 | $6,721 | Implemented |
SU0400 # 10 Y:2015 | 10 | 2015 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,639 | $5,931 | Implemented |
SU0400 # 11 Y:2015 | 11 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $443 | $865 | Implemented |
SU0400 # 14 Y:2015 | 14 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $47 | $163 | Implemented |