Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
497
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0414 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $26,496 | $1,980 | Implemented |
MI0414 # 03 Y:2022 | 03 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $35,363 | $35,990 | Implemented |
MI0414 # 02 Y:2022 | 02 | 2022 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $36,341 | $63,560 | Not Implemented |
MI0414 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $40,534 | $120 | Implemented |
UF0577 # 07 Y:2022 | 07 | 2022 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $1,440 | $3,987 | Not Implemented |
UF0577 # 10 Y:2022 | 10 | 2022 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $3,120 | $2,528 | Implemented |
UF0577 # 09 Y:2022 | 09 | 2022 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $1,049 | $200 | Implemented |
UF0577 # 01 Y:2022 | 01 | 2022 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,354 | $640 | Implemented |
UF0577 # 04 Y:2022 | 04 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,190 | $15,730 | Not Implemented |
UF0577 # 11 Y:2022 | 11 | 2022 | RECOVER AND REUSE WASTE MATERIAL | $28,657 | $31,000 | Implemented |
UF0577 # 08 Y:2022 | 08 | 2022 | INSTALL OCCUPANCY SENSORS | $1,187 | $4,373 | Not Implemented |
UF0577 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,991 | $304 | Implemented |
UF0577 # 06 Y:2022 | 06 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,972 | $0 | Implemented |
UF0577 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $3,407 | $2,618 | Implemented |
UF0577 # 03 Y:2022 | 03 | 2022 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $3,363 | $0 | Implemented |
UF0562 # 04 Y:2020 | 04 | 2020 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,128 | $7,733 | Not Implemented |
UF0562 # 06 Y:2020 | 06 | 2020 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,545 | $1,778 | Implemented |
UF0562 # 05 Y:2020 | 05 | 2020 | INSTALL OCCUPANCY SENSORS | $2,645 | $4,780 | Implemented |
UF0562 # 07 Y:2020 | 07 | 2020 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,484 | $2,380 | Not Implemented |
UF0562 # 08 Y:2020 | 08 | 2020 | USE PHOTOCELL CONTROLS | $904 | $0 | Implemented |
UF0562 # 03 Y:2020 | 03 | 2020 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,271 | $0 | Implemented |
UF0562 # 01 Y:2020 | 01 | 2020 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $30,571 | $24,600 | Not Implemented |
UF0562 # 02 Y:2020 | 02 | 2020 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,635 | $4,086 | Implemented |
MI0375 # 01 Y:2020 | 01 | 2020 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $9,722 | $20,153 | Implemented |
MI0375 # 09 Y:2020 | 09 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $339 | $984 | Implemented |