Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
152
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UA0057 # 08 Y:2010 | 08 | 2010 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $3,029 | $12,535 | Not Implemented |
UA0054 # 01 Y:2010 | 01 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $31,442 | $1,000 | Not Implemented |
UA0054 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,010 | $7,000 | Implemented |
UA0054 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $86,265 | $71,625 | Not Implemented |
UA0054 # 04 Y:2010 | 04 | 2010 | USE PHOTOCELL CONTROLS | $2,443 | $1,893 | Not Implemented |
UA0054 # 05 Y:2010 | 05 | 2010 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $42,638 | $40,400 | Not Implemented |
UA0054 # 06 Y:2010 | 06 | 2010 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $25,338 | $6,850 | Not Implemented |
UA0054 # 07 Y:2010 | 07 | 2010 | INSTALL TIMERS AND/OR THERMOSTATS | $4,372 | $3,230 | Implemented |
UA0020 # 01 Y:2008 | 01 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,259 | $60,237 | Implemented |
UA0020 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,022 | $15,096 | Implemented |
UA0020 # 03 Y:2008 | 03 | 2008 | USE RADIANT HEATER FOR SPOT HEATING | $7,553 | $13,800 | Implemented |
UA0020 # 04 Y:2008 | 04 | 2008 | INSTALL TIMERS AND/OR THERMOSTATS | $90 | $236 | Not Implemented |
UA0020 # 05 Y:2008 | 05 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $788 | $0 | Implemented |
UA0020 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $202 | $700 | Implemented |
UA0020 # 07 Y:2008 | 07 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $94 | $327 | Not Implemented |
UA0020 # 08 Y:2008 | 08 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $481 | $2,100 | Not Implemented |
UA0020 # 09 Y:2008 | 09 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,611 | $7,000 | Implemented |
UA0010 # 01 Y:2007 | 01 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,084 | $70,481 | Implemented |
UA0010 # 02 Y:2007 | 02 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,004 | $14,292 | Implemented |
UA0010 # 03 Y:2007 | 03 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $742 | $0 | Not Implemented |
UA0010 # 04 Y:2007 | 04 | 2007 | INSTALL TIMERS AND/OR THERMOSTATS | $426 | $590 | Implemented |
UA0010 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,616 | $700 | Implemented |
UA0010 # 06 Y:2007 | 06 | 2007 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $96 | $528 | Implemented |
UA0010 # 07 Y:2007 | 07 | 2007 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $933 | $0 | Implemented |
UA0010 # 08 Y:2007 | 08 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $155 | $320 | Implemented |