Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
127
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0120 # 05 Y:1994 | 05 | 1994 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $1,905 | $1,500 | Not Implemented |
ME0110 # 01 Y:1994 | 01 | 1994 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $787 | $1,250 | Not Implemented |
ME0110 # 02 Y:1994 | 02 | 1994 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $368 | $400 | Implemented |
ME0110 # 03 Y:1994 | 03 | 1994 | KEEP BOILER TUBES CLEAN | $357 | $200 | Implemented |
ME0103 # 01 Y:1993 | 01 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,228 | $180 | Not Implemented |
ME0103 # 02 Y:1993 | 02 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,470 | $1,300 | Not Implemented |
ME0103 # 03 Y:1993 | 03 | 1993 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $69,216 | $175,000 | Not Implemented |
ME0103 # 04 Y:1993 | 04 | 1993 | SCHEDULE BAKING TIMES OF SMALL AND LARGE COMPONENTS | $8,100 | $20,000 | Not Implemented |
ME0103 # 05 Y:1993 | 05 | 1993 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,120 | $700 | Implemented |
ME0103 # 06 Y:1993 | 06 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,129 | $13,680 | Not Implemented |
ME0103 # 07 Y:1993 | 07 | 1993 | PAY UTILITY BILLS ON TIME | $2,223 | $0 | Implemented |
ME0102 # 01 Y:1993 | 01 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $486 | $90 | Not Implemented |
ME0102 # 02 Y:1993 | 02 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,485 | $8,690 | Not Implemented |
ME0102 # 03 Y:1993 | 03 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,038 | $7,200 | Implemented |
ME0102 # 04 Y:1993 | 04 | 1993 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,674 | $1,400 | Implemented |
ME0102 # 05 Y:1993 | 05 | 1993 | OPTIMIZE PLANT POWER FACTOR | $1,363 | $0 | Not Implemented |
MA0229 # 01 Y:1991 | 01 | 1991 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,565 | $30,000 | Not Implemented |
MA0229 # 02 Y:1991 | 02 | 1991 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,963 | $0 | Not Implemented |
MA0229 # 03 Y:1991 | 03 | 1991 | OPTIMIZE PLANT POWER FACTOR | $1,759 | $4,685 | Not Implemented |
MA0229 # 04 Y:1991 | 04 | 1991 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,388 | $4,900 | Implemented |
MA0229 # 05 Y:1991 | 05 | 1991 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $825 | $1,900 | Not Implemented |
MA0229 # 06 Y:1991 | 06 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $520 | $1,749 | Implemented |
MA0229 # 07 Y:1991 | 07 | 1991 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $430 | $170 | Implemented |
MA0013 # 01 Y:1985 | 01 | 1985 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $949 | $171 | Implemented |
MA0013 # 02 Y:1985 | 02 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $7,976 | $8,800 | Implemented |