Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

261

matching recommendations
Reset
SIC 35 Industrial Machinery And Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AS0502 # 07 Y:2021 07 2021 INSTALL OCCUPANCY SENSORS $350 $1,131 Not Implemented
AS0502 # 01 Y:2021 01 2021 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $12,647 $200 Not Implemented
AS0502 # 05 Y:2021 05 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $393 $1,127 Implemented
AS0502 # 08 Y:2021 08 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $168 $375 Implemented
AS0502 # 03 Y:2021 03 2021 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,685 $2,400 Not Implemented
AS0502 # 04 Y:2021 04 2021 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $672 $284 Not Implemented
AS0502 # 02 Y:2021 02 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $11,703 $13,532 Implemented
AS0502 # 06 Y:2021 06 2021 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $359 $793 Implemented
AS0461 # 01 Y:2018 01 2018 RECOVER AND REUSE WASTE MATERIAL $11,063 $0 Not Implemented
AS0461 # 03 Y:2018 03 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,690 $6,300 Implemented
AS0461 # 02 Y:2018 02 2018 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $6,390 $30,436 Implemented
AS0461 # 04 Y:2018 04 2018 INSTALL OCCUPANCY SENSORS $2,926 $1,565 Not Implemented
AS0446 # 03 Y:2017 03 2017 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $982 $950 Not Implemented
AS0446 # 01 Y:2017 01 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,695 $180 Implemented
AS0446 # 02 Y:2017 02 2017 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,288 $1,482 Not Implemented
AS0434 # 03 Y:2017 03 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,405 $1,200 Not Implemented
AS0434 # 04 Y:2017 04 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,250 $2,513 Not Implemented
AS0434 # 01 Y:2017 01 2017 UPGRADE CONTROLS ON COMPRESSORS $68,034 $6,582 Not Implemented
AS0434 # 06 Y:2017 06 2017 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $461 $450 Not Implemented
AS0434 # 05 Y:2017 05 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,564 $60 Not Implemented
AS0434 # 07 Y:2017 07 2017 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $307 $60 Implemented
AS0434 # 02 Y:2017 02 2017 UPGRADE CONTROLS ON COMPRESSORS $43,502 $4,394 Not Implemented
AS0431 # 04 Y:2006 04 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $401 $1,500 n/a
AS0431 # 02 Y:2006 02 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,413 $1,500 n/a
AS0431 # 03 Y:2006 03 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $529 $1,500 n/a