Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
51
matching recommendationsSIC | 351 | Engines And Turbines |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0113 # 10 Y:2013 | 10 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $494 | $620 | Implemented |
MZ0113 # 09 Y:2013 | 09 | 2013 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $545 | $902 | Implemented |
MZ0113 # 08 Y:2013 | 08 | 2013 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,620 | $900 | Implemented |
MZ0113 # 07 Y:2013 | 07 | 2013 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,948 | $50 | Implemented |
MZ0113 # 05 Y:2013 | 05 | 2013 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,613 | $4,973 | Implemented |
MZ0113 # 04 Y:2013 | 04 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,882 | $1,698 | Implemented |
MZ0113 # 03 Y:2013 | 03 | 2013 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $7,609 | $1,000 | Implemented |
MZ0113 # 02 Y:2013 | 02 | 2013 | INSTALL SKYLIGHTS | $14,502 | $50,050 | Not Implemented |
MZ0113 # 06 Y:2013 | 06 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $3,575 | $3,500 | Implemented |
MZ0113 # 01 Y:2013 | 01 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $17,414 | $8,758 | Implemented |
MZ0097 # 02 Y:2012 | 02 | 2012 | INSULATE BARE EQUIPMENT | $106,168 | $10,690 | Not Implemented |
MZ0097 # 03 Y:2012 | 03 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $60,715 | $105,000 | Not Implemented |
MZ0097 # 04 Y:2012 | 04 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $49,961 | $5,000 | Not Implemented |
MZ0097 # 05 Y:2012 | 05 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $29,305 | $35,000 | Implemented |
MZ0097 # 06 Y:2012 | 06 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,968 | $450 | Implemented |
MZ0097 # 07 Y:2012 | 07 | 2012 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,420 | $2,000 | Not Implemented |
MZ0097 # 01 Y:2012 | 01 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $230,479 | $107,601 | Not Implemented |
MO0199 # 03 Y:1997 | 03 | 1997 | CROSS-TRAIN PERSONNEL TO AVOID LOST TIME | $25,800 | $20,000 | Implemented |
MO0199 # 02 Y:1997 | 02 | 1997 | RECOVER AND REUSE COOLING WATER | $20,939 | $19,000 | Implemented |
MO0199 # 01 Y:1997 | 01 | 1997 | RECOVERY METALS FROM RINSE WATER(EVAP., ION EXCHANGE, RO, ELECTROLYSIS, ELECTRODIALYSIS) AND REUSE RINSE WATER | $216,153 | $80,000 | Implemented |
MO0199 # 04 Y:1997 | 04 | 1997 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $18,045 | $15,000 | Implemented |
MO0199 # 05 Y:1997 | 05 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $10,080 | $10,000 | Implemented |
MO0199 # 06 Y:1997 | 06 | 1997 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $4,940 | $9,500 | Implemented |
MO0199 # 07 Y:1997 | 07 | 1997 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $38,120 | $550 | Implemented |
MO0199 # 08 Y:1997 | 08 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $10,447 | $28,282 | Implemented |