Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
436
matching recommendationsSIC | 352 | Farm And Garden Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0381 # 01 Y:2010 | 01 | 2010 | USE OPTIMUM TEMPERATURE | $2,152 | $0 | Implemented |
SF0381 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,745 | $23,088 | Implemented |
SF0381 # 06 Y:2010 | 06 | 2010 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $3,502 | $6,175 | Implemented |
SF0381 # 07 Y:2010 | 07 | 2010 | INSTALL OCCUPANCY SENSORS | $841 | $2,812 | Implemented |
IA0425 # 06 Y:2008 | 06 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,859 | $2,000 | Implemented |
IA0425 # 04 Y:2008 | 04 | 2008 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $50,635 | $291,629 | Implemented |
IA0425 # 03 Y:2008 | 03 | 2008 | INSTALL TIMERS AND/OR THERMOSTATS | $15,476 | $600 | Implemented |
LL0287 # 04 Y:2008 | 04 | 2008 | INSTALL OCCUPANCY SENSORS | $1,821 | $60 | Implemented |
LL0287 # 03 Y:2008 | 03 | 2008 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,155 | $456 | Implemented |
UD0765 # 01 Y:2007 | 01 | 2007 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $9,128 | $3,450 | Implemented |
UD0765 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,922 | $7,945 | Implemented |
UD0765 # 04 Y:2007 | 04 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,808 | $3,777 | Implemented |
UD0765 # 05 Y:2007 | 05 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,628 | $915 | Implemented |
UD0765 # 06 Y:2007 | 06 | 2007 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $997 | $0 | Implemented |
UD0765 # 07 Y:2007 | 07 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $764 | $883 | Implemented |
UD0765 # 08 Y:2007 | 08 | 2007 | INSTALL SKYLIGHTS | $666 | $2,421 | Implemented |
UD0765 # 09 Y:2007 | 09 | 2007 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $500 | $0 | Implemented |
UD0765 # 10 Y:2007 | 10 | 2007 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $496 | $0 | Implemented |
UD0765 # 11 Y:2007 | 11 | 2007 | INSTALL SKYLIGHTS | $354 | $1,083 | Implemented |
UD0765 # 12 Y:2007 | 12 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $233 | $500 | Implemented |
UD0765 # 13 Y:2007 | 13 | 2007 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $216 | $324 | Implemented |
WI0523 # 03 Y:2006 | 03 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,347 | $1,000 | Implemented |
WI0523 # 06 Y:2006 | 06 | 2006 | USE SYNTHETIC LUBRICANT | $1,970 | $0 | Implemented |
IA0391 # 07 Y:2006 | 07 | 2006 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $804 | $600 | Implemented |
IA0391 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $3,433 | $1,735 | Implemented |