Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsSIC | 3531 | Construction Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CW0122 # 06 Y:2022 | 06 | 2022 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $42,376 | $188,648 | n/a |
CW0122 # 05 Y:2022 | 05 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $13,037 | $60,000 | n/a |
CW0122 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $25,171 | $73,990 | n/a |
CW0122 # 03 Y:2022 | 03 | 2022 | CONVERT TO ROBOTIC PAINTING | $102,960 | $48,500 | n/a |
CW0122 # 02 Y:2022 | 02 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,767 | $400 | n/a |
CW0122 # 01 Y:2022 | 01 | 2022 | TREAT AND REUSE RINSE WATERS | $11,974 | $2,500 | n/a |
CW0121 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,231 | $26,058 | Implemented |
CW0121 # 12 Y:2022 | 12 | 2022 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $48,258 | $14,344 | Implemented |
CW0121 # 11 Y:2022 | 11 | 2022 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $545 | $90 | Not Implemented |
CW0121 # 09 Y:2022 | 09 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $608 | $165 | Implemented |
CW0121 # 01 Y:2022 | 01 | 2022 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $3,129 | $400 | Implemented |
CW0121 # 03 Y:2022 | 03 | 2022 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $3,746 | $265 | Implemented |
CW0121 # 04 Y:2022 | 04 | 2022 | CONVERT TO ROBOTIC PAINTING | $93,600 | $33,000 | Not Implemented |
CW0121 # 05 Y:2022 | 05 | 2022 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $31,088 | $86,330 | Implemented |
CW0121 # 06 Y:2022 | 06 | 2022 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $461 | $517 | Implemented |
CW0121 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,581 | $0 | Implemented |
CW0121 # 08 Y:2022 | 08 | 2022 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $925 | $810 | Not Implemented |
CW0121 # 10 Y:2022 | 10 | 2022 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $6,639 | $5,500 | Implemented |
UD0698 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $84 | $270 | Implemented |
UD0698 # 07 Y:2004 | 07 | 2004 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $739 | $845 | Implemented |
UD0698 # 06 Y:2004 | 06 | 2004 | IMPROVE LUBRICATION PRACTICES | $1,693 | $0 | Implemented |
UD0698 # 05 Y:2004 | 05 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,310 | $0 | Not Implemented |
UD0698 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,898 | $1,635 | Implemented |
UD0698 # 01 Y:2004 | 01 | 2004 | REDUCE FLUID FLOW RATES | $12,697 | $0 | Implemented |
UD0698 # 02 Y:2004 | 02 | 2004 | COMBINE UTILITY METERS | $11,340 | $0 | Not Implemented |