Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
22
matching recommendationsSIC | 3531 | Construction Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0754 # 03 Y:2022 | 03 | 2022 | FILTER AND REUSE HYDRAULIC OIL | $13,859 | $65,000 | Not Implemented |
OR0754 # 02 Y:2022 | 02 | 2022 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,033 | $3,560 | Implemented |
OR0754 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,871 | $2,675 | Implemented |
OR0748 # 05 Y:2022 | 05 | 2022 | INSULATE BARE EQUIPMENT | $2,032 | $9,520 | Implemented |
OR0748 # 04 Y:2022 | 04 | 2022 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $99,431 | $292,453 | Implemented |
OR0748 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $3,913 | $10,533 | Implemented |
OR0748 # 02 Y:2022 | 02 | 2022 | FILTER AND REUSE HYDRAULIC OIL | $34,830 | $88,699 | Implemented |
OR0748 # 01 Y:2022 | 01 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,763 | $1,880 | Implemented |
OR0700 # 01 Y:2018 | 01 | 2018 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $7,430 | $1,495 | Not Implemented |
OR0700 # 03 Y:2018 | 03 | 2018 | REPOSITION OVEN WALLS TO REDUCE HEATED SPACE | $2,175 | $5,389 | Not Implemented |
OR0700 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,059 | $6,826 | Not Implemented |
OR0065 # 06 Y:1989 | 06 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,845 | $2,000 | Implemented |
OR0065 # 05 Y:1989 | 05 | 1989 | OPTIMIZE PLANT POWER FACTOR | $5,181 | $5,400 | Not Implemented |
OR0065 # 04 Y:1989 | 04 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $394 | $279 | Implemented |
OR0065 # 03 Y:1989 | 03 | 1989 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $338 | $150 | Implemented |
OR0065 # 02 Y:1989 | 02 | 1989 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,603 | $1,075 | Not Implemented |
OR0065 # 01 Y:1989 | 01 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,924 | $2,050 | Implemented |
OR0016 # 01 Y:1988 | 01 | 1988 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,173 | $0 | Implemented |
OR0016 # 05 Y:1988 | 05 | 1988 | OPTIMIZE PLANT POWER FACTOR | $1,972 | $4,110 | Not Implemented |
OR0016 # 04 Y:1988 | 04 | 1988 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $147 | $200 | Implemented |
OR0016 # 03 Y:1988 | 03 | 1988 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,304 | $200 | Implemented |
OR0016 # 02 Y:1988 | 02 | 1988 | INSTALL SET-BACK TIMERS | $4,547 | $270 | Implemented |