Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 354 | Metalworking Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0644 # 01 Y:2019 | 01 | 2019 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $28,909 | $65,575 | Implemented |
NC0644 # 02 Y:2019 | 02 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $23,191 | $30,000 | Implemented |
NC0644 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,841 | $25,826 | Implemented |
NC0375 # 03 Y:2008 | 03 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,903 | $7,500 | Implemented |
NC0375 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,473 | $1,680 | Implemented |
NC0375 # 05 Y:2008 | 05 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,999 | $4,820 | Implemented |
NC0375 # 06 Y:2008 | 06 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $1,686 | $2,173 | Implemented |
NC0199 # 06 Y:2000 | 06 | 2000 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $5,140 | $0 | Implemented |
NC0199 # 05 Y:2000 | 05 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,352 | $210 | Implemented |
NC0199 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,374 | $7,490 | Implemented |
NC0144 # 04 Y:1998 | 04 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,617 | $4,731 | Implemented |
NC0144 # 05 Y:1998 | 05 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $113 | $200 | Implemented |
NC0144 # 06 Y:1998 | 06 | 1998 | METER WASTE WATER | $1,464 | $200 | Implemented |
NC0144 # 07 Y:1998 | 07 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $5,550 | $2,700 | Implemented |
NC0144 # 02 Y:1998 | 02 | 1998 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,664 | $1,000 | Implemented |
AT0025 # 06 Y:1985 | 06 | 1985 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,470 | $0 | Implemented |
AT0025 # 03 Y:1985 | 03 | 1985 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $74,001 | $9,900 | Implemented |