Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,555
matching recommendationsSIC | 355 | Special Industry Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0593 # 02 Y:2020 | 02 | 2020 | UPGRADE CONTROLS ON COMPRESSORS | $9,611 | $20,330 | Implemented |
WV0593 # 03 Y:2020 | 03 | 2020 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,095 | $4,464 | Not Implemented |
WV0593 # 04 Y:2020 | 04 | 2020 | RECYCLE WHITE WATER | $8,377 | $11,018 | Not Implemented |
WV0593 # 05 Y:2020 | 05 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,139 | $1,114 | Implemented |
WV0593 # 06 Y:2020 | 06 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,451 | $44 | Implemented |
WV0593 # 07 Y:2020 | 07 | 2020 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $2,437 | $4,000 | Not Implemented |
WV0593 # 08 Y:2020 | 08 | 2020 | DEVELOP A REPAIR/REPLACE POLICY | $1,877 | $318 | Implemented |
WV0593 # 09 Y:2020 | 09 | 2020 | INSTALL OCCUPANCY SENSORS | $1,845 | $3,682 | Implemented |
WV0593 # 10 Y:2020 | 10 | 2020 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,826 | $3,500 | Not Implemented |
MZ0275 # 01 Y:2020 | 01 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,533 | $24,500 | Not Implemented |
MZ0275 # 02 Y:2020 | 02 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,790 | $7,081 | Not Implemented |
MZ0275 # 03 Y:2020 | 03 | 2020 | INSTALL OCCUPANCY SENSORS | $5,169 | $10,500 | Not Implemented |
MZ0275 # 04 Y:2020 | 04 | 2020 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,201 | $3,250 | Not Implemented |
MZ0275 # 05 Y:2020 | 05 | 2020 | USE PHOTOCELL CONTROLS | $1,385 | $1,440 | Not Implemented |
MZ0275 # 06 Y:2020 | 06 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,072 | $2,400 | Not Implemented |
IP0128 # 01 Y:2019 | 01 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $331 | $0 | Implemented |
IP0128 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,334 | $76 | Implemented |
IP0128 # 03 Y:2019 | 03 | 2019 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $1,067 | $66 | Not Implemented |
IP0128 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $2,633 | $1,575 | Implemented |
IP0128 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,549 | $36,977 | Implemented |
LE0484 # 01 Y:2019 | 01 | 2019 | INSTALL TIMERS AND/OR THERMOSTATS | $7,603 | $0 | Implemented |
LE0484 # 02 Y:2019 | 02 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,873 | $6,000 | Implemented |
LE0484 # 03 Y:2019 | 03 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,670 | $2,500 | Implemented |
LE0484 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,910 | $23,990 | Implemented |
LE0484 # 05 Y:2019 | 05 | 2019 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,805 | $5,500 | Implemented |