Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsSIC | 355 | Special Industry Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0249 # 05 Y:2021 | 05 | 2021 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,067 | $0 | Implemented |
IC0249 # 04 Y:2021 | 04 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,062 | $18,089 | Not Implemented |
IC0249 # 03 Y:2021 | 03 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,949 | $440 | Implemented |
IC0249 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,374 | $4,100 | Implemented |
IC0249 # 01 Y:2021 | 01 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,457 | $154 | Not Implemented |
IP0128 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,334 | $76 | Implemented |
IP0128 # 01 Y:2019 | 01 | 2019 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $331 | $0 | Implemented |
IP0128 # 05 Y:2019 | 05 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,549 | $36,977 | Implemented |
IP0128 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $2,633 | $1,575 | Implemented |
IP0128 # 03 Y:2019 | 03 | 2019 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $1,067 | $66 | Not Implemented |
IP0118 # 03 Y:2019 | 03 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,045 | $2,439 | Not Implemented |
IP0118 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,021 | $10,215 | Implemented |
IP0118 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,154 | $1,526 | Implemented |
IP0118 # 01 Y:2019 | 01 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,954 | $824 | Implemented |
IP0045 # 05 Y:2015 | 05 | 2015 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,201 | $17,250 | Implemented |
IP0045 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,242 | $417 | Implemented |
IP0045 # 03 Y:2015 | 03 | 2015 | BURN A LESS EXPENSIVE GRADE OF FUEL | $25,783 | $1,054 | Implemented |
IP0045 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $401 | $0 | Implemented |
IP0045 # 01 Y:2015 | 01 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $1,605 | $0 | Implemented |
ND0340 # 01 Y:1999 | 01 | 1999 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $9,628 | $0 | Not Implemented |
ND0340 # 02 Y:1999 | 02 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $329 | $240 | Implemented |
ND0340 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $351 | $510 | Not Implemented |
ND0340 # 06 Y:1999 | 06 | 1999 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $20 | $0 | Implemented |
ND0340 # 05 Y:1999 | 05 | 1999 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $134 | $500 | Not Implemented |
ND0340 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $297 | $40 | Not Implemented |