Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,477
matching recommendationsSIC | 356 | General Industrial Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0017 # 03 Y:1988 | 03 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,124 | $2,325 | Implemented |
WI0017 # 06 Y:1988 | 06 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $371 | $500 | Implemented |
KU0242 # 01 Y:1988 | 01 | 1988 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,183 | $6,000 | Implemented |
KU0242 # 02 Y:1988 | 02 | 1988 | REDESIGN PROCESS | $4,705 | $2,080 | Implemented |
KU0242 # 04 Y:1988 | 04 | 1988 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,965 | $3,600 | Implemented |
KU0242 # 06 Y:1988 | 06 | 1988 | INSTALL AUTOMATIC STACK DAMPER | $1,519 | $1,800 | Implemented |
KU0242 # 07 Y:1988 | 07 | 1988 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $1,236 | $1,500 | Implemented |
KU0242 # 08 Y:1988 | 08 | 1988 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $928 | $0 | Implemented |
KU0242 # 10 Y:1988 | 10 | 1988 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $487 | $500 | Implemented |
KU0242 # 11 Y:1988 | 11 | 1988 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $107 | $0 | Implemented |
MA0107 # 01 Y:1987 | 01 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,770 | $664 | Implemented |
MA0107 # 02 Y:1987 | 02 | 1987 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $132 | $0 | Implemented |
MA0107 # 03 Y:1987 | 03 | 1987 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $7,636 | $17,200 | Implemented |
MA0107 # 04 Y:1987 | 04 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $5,097 | $1,800 | Implemented |
KU0235 # 02 Y:1987 | 02 | 1987 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,844 | $0 | Implemented |
KU0235 # 03 Y:1987 | 03 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,582 | $400 | Implemented |
KU0235 # 04 Y:1987 | 04 | 1987 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,242 | $4,000 | Implemented |
KU0235 # 10 Y:1987 | 10 | 1987 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $162 | $0 | Implemented |
CO0092 # 01 Y:1987 | 01 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,461 | $500 | Implemented |
CO0092 # 02 Y:1987 | 02 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,213 | $3,000 | Implemented |
CO0092 # 03 Y:1987 | 03 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,081 | $250 | Implemented |
CO0092 # 04 Y:1987 | 04 | 1987 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,490 | $2,000 | Implemented |
CO0092 # 06 Y:1987 | 06 | 1987 | REDUCE VENTILATION AIR | $300 | $36 | Implemented |
CO0092 # 07 Y:1987 | 07 | 1987 | INSULATE BARE EQUIPMENT | $187 | $60 | Implemented |
CO0092 # 08 Y:1987 | 08 | 1987 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,609 | $10,000 | Implemented |