Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,257
matching recommendationsSIC | 356 | General Industrial Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0485 # 10 Y:2019 | 10 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,242 | $26,026 | Implemented |
SU0485 # 11 Y:2019 | 11 | 2019 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $347 | $1,404 | Not Implemented |
UK1906 # 01 Y:2019 | 01 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $483 | $1,100 | n/a |
UK1906 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,725 | $0 | n/a |
UK1906 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,355 | $2,630 | n/a |
UK1906 # 04 Y:2019 | 04 | 2019 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,341 | $2,275 | n/a |
UK1906 # 05 Y:2019 | 05 | 2019 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $288 | $1,045 | n/a |
UK1906 # 06 Y:2019 | 06 | 2019 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,304 | $660 | n/a |
UK1906 # 07 Y:2019 | 07 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,766 | $0 | n/a |
UK1906 # 08 Y:2019 | 08 | 2019 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,392 | $0 | n/a |
UK1906 # 09 Y:2019 | 09 | 2019 | USE RADIANT HEATER FOR SPOT HEATING | $8,769 | $4,160 | n/a |
UK1906 # 10 Y:2019 | 10 | 2019 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $107 | $223 | n/a |
UK1906 # 11 Y:2019 | 11 | 2019 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,742 | $0 | n/a |
UK1906 # 12 Y:2019 | 12 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,165 | $48,242 | n/a |
UK1906 # 13 Y:2019 | 13 | 2019 | USE PHOTOCELL CONTROLS | $2,056 | $0 | n/a |
UK1906 # 14 Y:2019 | 14 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $36 | $36 | n/a |
UK1906 # 15 Y:2019 | 15 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,287 | $0 | n/a |
MZ0272 # 01 Y:2019 | 01 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,929 | $250 | Implemented |
MZ0272 # 02 Y:2019 | 02 | 2019 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $241 | $105 | Implemented |
MZ0272 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,572 | $29,988 | Not Implemented |
MZ0272 # 04 Y:2019 | 04 | 2019 | INSTALL OCCUPANCY SENSORS | $2,084 | $1,860 | Implemented |
MZ0272 # 05 Y:2019 | 05 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $262 | $1,040 | Not Implemented |
MZ0272 # 06 Y:2019 | 06 | 2019 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,655 | $180 | Implemented |
MZ0272 # 07 Y:2019 | 07 | 2019 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $31,952 | $68,000 | Not Implemented |
MZ0272 # 08 Y:2019 | 08 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $331 | $180 | Not Implemented |