Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
18
matching recommendationsSIC | 3569 | General Industrial Machinery, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0574 # 05 Y:2019 | 05 | 2019 | REDUCE SCRAP PRODUCTION | $25,514 | $1,500 | Implemented |
SD0574 # 02 Y:2019 | 02 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $886 | $300 | Implemented |
SD0574 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,259 | $0 | Implemented |
SD0551 # 05 Y:2017 | 05 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $169 | $200 | Implemented |
SD0551 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $433 | $1,500 | Implemented |
SD0551 # 03 Y:2017 | 03 | 2017 | INSTALL OCCUPANCY SENSORS | $899 | $3,000 | Implemented |
SD0551 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,959 | $35,776 | Implemented |
SD0369 # 06 Y:2005 | 06 | 2005 | INSTALL OCCUPANCY SENSORS | $395 | $80 | Implemented |
SD0369 # 07 Y:2005 | 07 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $285 | $161 | Implemented |
SD0369 # 05 Y:2005 | 05 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,896 | $10,102 | Implemented |
SD0369 # 02 Y:2005 | 02 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $17,291 | $0 | Implemented |
SD0208 # 05 Y:1998 | 05 | 1998 | RECYCLE WHITE WATER | $12,375 | $5,000 | Implemented |
SD0208 # 04 Y:1998 | 04 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $3,843 | $2,700 | Implemented |
SD0194 # 01 Y:1998 | 01 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,625 | $5,210 | Implemented |
SD0194 # 07 Y:1998 | 07 | 1998 | RECOVER METALS FROM SPENT SOLUTIONS AND RECYCLE | $2,400 | $1,000 | Implemented |
SD0194 # 05 Y:1998 | 05 | 1998 | USE OPTIMUM THICKNESS INSULATION | $2,213 | $1,559 | Implemented |
SD0194 # 04 Y:1998 | 04 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $706 | $1,150 | Implemented |
SD0194 # 03 Y:1998 | 03 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,430 | $450 | Implemented |