Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
26
matching recommendationsSIC | 358 | Refrigeration And Service Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0258 # 07 Y:2000 | 07 | 2000 | CONVERT TO AQUEOUS CLEANING SYSTEM | $56,437 | $420 | Not Implemented |
IA0258 # 06 Y:2000 | 06 | 2000 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $47,250 | $7,175 | Not Implemented |
IA0258 # 05 Y:2000 | 05 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,920 | $1,206 | Implemented |
IA0258 # 04 Y:2000 | 04 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $288 | $25 | Implemented |
IA0258 # 03 Y:2000 | 03 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $986 | $40 | Not Implemented |
IA0258 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,870 | $753 | Implemented |
IA0258 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $23,446 | $45,125 | Not Implemented |
IA0242 # 04 Y:2000 | 04 | 2000 | TURN OFF EQUIPMENT WHEN NOT IN USE | $276 | $45 | Not Implemented |
IA0242 # 09 Y:2000 | 09 | 2000 | APPLY FOR INVESTMENT INCENTIVES | $3,531 | $250 | Not Implemented |
IA0242 # 08 Y:2000 | 08 | 2000 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $4,883 | $123 | Not Implemented |
IA0242 # 07 Y:2000 | 07 | 2000 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $448 | $890 | Not Implemented |
IA0242 # 06 Y:2000 | 06 | 2000 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $1,636 | $675 | Not Implemented |
IA0242 # 05 Y:2000 | 05 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $79 | $25 | Not Implemented |
IA0242 # 03 Y:2000 | 03 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $604 | $2,000 | Not Implemented |
IA0242 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $833 | $1,167 | Not Implemented |
IA0242 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,701 | $169 | Not Implemented |
IA0223 # 01 Y:1999 | 01 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,307 | $2,670 | n/a |
IA0223 # 10 Y:1999 | 10 | 1999 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $3,779 | $1,400 | n/a |
IA0223 # 09 Y:1999 | 09 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $40,016 | $218 | n/a |
IA0223 # 08 Y:1999 | 08 | 1999 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $70,029 | $25,372 | n/a |
IA0223 # 07 Y:1999 | 07 | 1999 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $17,424 | $7,400 | n/a |
IA0223 # 06 Y:1999 | 06 | 1999 | INSTALL OCCUPANCY SENSORS | $144 | $732 | n/a |
IA0223 # 05 Y:1999 | 05 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $741 | $50 | n/a |
IA0223 # 04 Y:1999 | 04 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,282 | $653 | n/a |
IA0223 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,841 | $0 | n/a |