Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

53

matching recommendations
Reset
SIC 359 Industrial Machinery, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
IA0348 # 08 Y:2004 08 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $16,653 $4,596 Implemented
IA0348 # 02 Y:2004 02 2004 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $1,336 $475 Not Implemented
IA0348 # 01 Y:2004 01 2004 OPTIMIZE PLANT POWER FACTOR $9,818 $10,704 Implemented
IA0348 # 03 Y:2004 03 2004 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $651 $146 Implemented
IA0348 # 07 Y:2004 07 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $383 $120 Not Implemented
IA0348 # 04 Y:2004 04 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,888 $535 Implemented
IA0348 # 05 Y:2004 05 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,829 $14,216 Implemented
IA0348 # 06 Y:2004 06 2004 DIRECT WARMEST AIR TO COMBUSTION INTAKE $193 $438 Not Implemented
OR0470 # 03 Y:2004 03 2004 ELIMINATE/REDUCE AN OPERATION $9,627 $250 Not Implemented
OR0470 # 04 Y:2004 04 2004 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $2,990 $300 Not Implemented
OR0470 # 05 Y:2004 05 2004 ELIMINATE/REDUCE AN OPERATION $1,185 $165 Implemented
OR0470 # 01 Y:2004 01 2004 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $92,000 $1,200 Not Implemented
OR0470 # 02 Y:2004 02 2004 ELIMINATE/REDUCE REDUNDANT INSPECTIONS $11,400 $2,800 Not Implemented
BD0270 # 06 Y:2004 06 2004 RECOVER WASTE HEAT FROM EQUIPMENT $2,453 $3,500 Not Implemented
BD0270 # 12 Y:2004 12 2004 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL $0 $3,000 Not Implemented
BD0270 # 11 Y:2004 11 2004 MINIMIZE WATER USAGE $3,135 $1,320 Not Implemented
BD0270 # 10 Y:2004 10 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $353 $168 Implemented
BD0270 # 09 Y:2004 09 2004 USE PHOTOCELL CONTROLS $1,040 $320 Implemented
BD0270 # 08 Y:2004 08 2004 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $2,173 $75 Implemented
BD0270 # 07 Y:2004 07 2004 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,382 $750 Implemented
BD0270 # 05 Y:2004 05 2004 RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT $4,757 $1,000 Not Implemented
BD0270 # 04 Y:2004 04 2004 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $11,396 $480 Not Implemented
BD0270 # 03 Y:2004 03 2004 USE RADIANT HEATER FOR SPOT HEATING $11,491 $18,616 Not Implemented
BD0270 # 02 Y:2004 02 2004 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $13,615 $24,000 Implemented
BD0270 # 01 Y:2004 01 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $20,872 $0 Implemented