Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
753
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0415 # 09 Y:2009 | 09 | 2009 | INSTALL OCCUPANCY SENSORS | $154 | $347 | Implemented |
SF0370 # 01 Y:2009 | 01 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $316 | $0 | Not Implemented |
SF0370 # 02 Y:2009 | 02 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,936 | $2,464 | Not Implemented |
SF0370 # 03 Y:2009 | 03 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $684 | $849 | Not Implemented |
SF0370 # 04 Y:2009 | 04 | 2009 | INSULATE BARE EQUIPMENT | $942 | $2,473 | Not Implemented |
SF0370 # 05 Y:2009 | 05 | 2009 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $972 | $2,956 | Not Implemented |
SF0370 # 06 Y:2009 | 06 | 2009 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,614 | $7,537 | Not Implemented |
SF0370 # 07 Y:2009 | 07 | 2009 | INSTALL OCCUPANCY SENSORS | $1,231 | $10,326 | Not Implemented |
SF0370 # 08 Y:2009 | 08 | 2009 | USE SOLAR HEAT TO MAKE ELECTRICTY | $74,612 | $654,810 | Not Implemented |
SD0408 # 01 Y:2008 | 01 | 2008 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,619 | $223,150 | Not Implemented |
SD0408 # 02 Y:2008 | 02 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,994 | $2,875 | Implemented |
SD0408 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,149 | $5,702 | Implemented |
SD0408 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,048 | $4,720 | Implemented |
SD0408 # 05 Y:2008 | 05 | 2008 | INSTALL SKYLIGHTS | $431 | $2,016 | Not Implemented |
SD0408 # 06 Y:2008 | 06 | 2008 | INSTALL OCCUPANCY SENSORS | $83 | $246 | Implemented |
LM0119 # 01 Y:2006 | 01 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $500 | $374 | Not Implemented |
LM0119 # 02 Y:2006 | 02 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $746 | $0 | Not Implemented |
LM0119 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $859 | $100 | Not Implemented |
LM0119 # 04 Y:2006 | 04 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $58,500 | $160,200 | Not Implemented |
LM0119 # 05 Y:2006 | 05 | 2006 | CONDENSE OPERATION INTO ONE BUILDING | $39,440 | $0 | Not Implemented |
LM0119 # 06 Y:2006 | 06 | 2006 | CONDENSE OPERATION INTO ONE BUILDING | $3,375,000 | $500,000 | Implemented |
LM0115 # 01 Y:2006 | 01 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,535 | $200 | Not Implemented |
LM0115 # 02 Y:2006 | 02 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $947 | $200 | Not Implemented |
LM0115 # 03 Y:2006 | 03 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,573 | $0 | Not Implemented |
LM0115 # 04 Y:2006 | 04 | 2006 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $55,692 | $7,875 | Not Implemented |