Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
739
matching recommendationsSIC | 361 | Electric Distribution Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0157 # 01 Y:1999 | 01 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,968 | $1,500 | Not Implemented |
NC0157 # 02 Y:1999 | 02 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,307 | $240 | Not Implemented |
NC0157 # 03 Y:1999 | 03 | 1999 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $6,654 | $2,000 | Not Implemented |
NC0157 # 04 Y:1999 | 04 | 1999 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $98,761 | $465,000 | Not Implemented |
NC0157 # 05 Y:1999 | 05 | 1999 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $17,776 | $20,000 | Not Implemented |
NC0157 # 06 Y:1999 | 06 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,015 | $3,000 | Implemented |
NC0157 # 07 Y:1999 | 07 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $8,000 | $200 | Implemented |
NC0157 # 08 Y:1999 | 08 | 1999 | ADD ADDITIONAL PRODUCTION SHIFT | $100,000 | $1,000 | Not Implemented |
NC0157 # 09 Y:1999 | 09 | 1999 | MODIFY STARTUP/SHUTDOWN TIMES | $3,193 | $0 | Implemented |
TN0651 # 01 Y:1999 | 01 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $23,000 | $21,000 | Not Implemented |
TN0651 # 02 Y:1999 | 02 | 1999 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $9,040 | $9,140 | Implemented |
TN0651 # 03 Y:1999 | 03 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,840 | $8,000 | Not Implemented |
TN0651 # 04 Y:1999 | 04 | 1999 | INSULATE BARE EQUIPMENT | $3,020 | $1,605 | Implemented |
TN0651 # 05 Y:1999 | 05 | 1999 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $2,625 | $900 | Not Implemented |
TN0651 # 06 Y:1999 | 06 | 1999 | REPROCESS SPENT OILS ON SITE FOR RE-USE | $1,465 | $2,420 | Not Implemented |
TN0651 # 07 Y:1999 | 07 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $880 | $1,120 | Not Implemented |
WV0156 # 01 Y:1999 | 01 | 1999 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $17,572 | $15,591 | Not Implemented |
WV0156 # 02 Y:1999 | 02 | 1999 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $1,158 | $672 | Implemented |
WV0156 # 03 Y:1999 | 03 | 1999 | BURN A LESS EXPENSIVE GRADE OF FUEL | $4,324 | $4,800 | Not Implemented |
WV0156 # 04 Y:1999 | 04 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,399 | $1,876 | Implemented |
WV0156 # 05 Y:1999 | 05 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $732 | $671 | Implemented |
WV0156 # 06 Y:1999 | 06 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,548 | $144 | Implemented |
WV0156 # 07 Y:1999 | 07 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,743 | $60 | Implemented |
WV0156 # 08 Y:1999 | 08 | 1999 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,888 | $4,000 | Not Implemented |
WV0156 # 09 Y:1999 | 09 | 1999 | REPLACE BOILER | $2,866 | $49,515 | Not Implemented |