Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
547
matching recommendationsSIC | 362 | Electrical Industrial Apparatus |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UC2306 # 07 Y:2023 | 07 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,153 | $34,274 | Implemented |
UC2306 # 03 Y:2023 | 03 | 2023 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $375 | $0 | Implemented |
UC2306 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,636 | $11,635 | Implemented |
UU0218 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,223 | $53,198 | Implemented |
UU0218 # 07 Y:2023 | 07 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $512 | $161 | Implemented |
UU0218 # 02 Y:2023 | 02 | 2023 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $7,404 | $5,700 | Implemented |
UU0218 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,861 | $721 | Implemented |
SU0521 # 07 Y:2022 | 07 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,254 | $800 | Implemented |
SU0521 # 05 Y:2022 | 05 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,226 | $380 | Implemented |
SU0521 # 04 Y:2022 | 04 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,111 | $0 | Implemented |
SU0521 # 01 Y:2022 | 01 | 2022 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,147 | $0 | Implemented |
SU0521 # 03 Y:2022 | 03 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $40 | $0 | Implemented |
SU0521 # 02 Y:2022 | 02 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,565 | $0 | Implemented |
LE0502 # 01 Y:2021 | 01 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $1,768 | $200 | Implemented |
LE0502 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,993 | $17,900 | Implemented |
LE0502 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $757 | $1,800 | Implemented |
LE0502 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,020 | $17,500 | Implemented |
OK1025 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,733 | $8,651 | Implemented |
OK1025 # 04 Y:2020 | 04 | 2020 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,427 | $1,500 | Implemented |
OK1025 # 02 Y:2020 | 02 | 2020 | INSTALL TIMERS AND/OR THERMOSTATS | $3,684 | $2,420 | Implemented |
OK1025 # 03 Y:2020 | 03 | 2020 | INSULATE BARE EQUIPMENT | $5,805 | $65 | Implemented |
OK1025 # 01 Y:2020 | 01 | 2020 | USE RADIANT HEATER FOR SPOT HEATING | $34,672 | $127,500 | Implemented |
WM0140 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,984 | $27,284 | Implemented |
WM0140 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,092 | $0 | Implemented |
WM0140 # 01 Y:2019 | 01 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $18,432 | $51,563 | Implemented |